Commodity 2
Lorem ipsum dolor sit amet consectetur. Iaculis morbi a purus donec faucibus condime...
July 4, 2025
Commodity
VANCOUVER, Canada, July 04, 2025 (GLOBE NEWSWIRE) -- Sonoro Gold Corp. (TSXV: SGO | OTCQB: SMOFF | FRA: 23SP) (“Sonoro” or the “Company”) is pleased to announce that through its wholly owned Mexican subsidiary Minera Mar De Plata S.A. DE C.V. (“MMP
July 3, 2025
July 3, 2025 ( ACCESS Newswire) - Goldgroup Mining Inc . ("Goldgroup" or the "Company") (TSXV:GGA)(OTCID:GGAZF) is pleased to report that it has closed the previously announced acquisition of a 100% interest in the fully permitted for construc
NOT FOR DISTRIBUTION TO U.S. NEWS WIRE SERVICES OR DISSEMINATION IN THE UNITED STATES. ROUYN-NORANDA, Quebec, July 03, 2025 (GLOBE NEWSWIRE) -- Abcourt Mines Inc. (“ Abcourt ” or the “ Corporation ”) (TSX Venture: ABI) (OTCQB: ABMBF) is pleased t
July 3, 2025 (Source: Ero Copper Corp.) Vancouver, British Columbia – Ero Copper Corp. (TSX: ERO, NYSE: ERO) ("Ero" or the “Company”) is pleased to announce that the Tucumã Operation, located in Pará State, Brazil, achieved commercial production,
June 30, 2025
VANCOUVER, BC , June 30, 2025 /CNW/ - Aris Mining Corporation (Aris Mining or the Company) (TSX: ARIS ) (NYSE-A: ARMN) announces the successful installation and commissioning of a second processing mill at its high-grade Segovia Operations in Antioquia, Colombia . This expansion is a significant milestone in the Company's organic growth strategy and increases Segovia's processing capacity by 50%, from 2,000 to 3,000 tonnes per day (tpd). The second mill is fully integrated into the existing plant infrastructure and utilizes shared circuits for crushing, flotation, leaching and tailings filtration. The project was completed on schedule and within budget, with commissioning activities completed in June 2025 . Neil Woodyer , CEO, commented "The installation and commiss
June 23, 2025
June 23, 2025 (Australian Mining) - Hillgrove Resources has delivered first development ore from its Nugent underground deposit in Western Australia ahead of schedule, following development progress that topped expectations. The 1020 level crosscut successfully intersected the Nugent orebody, enabling early delivery of development ore to the Kanmantoo mill. ... This milestone marks a significant advancement in our strategic plan to accelerate ore production and increase throughput at Kanmantoo, which will flow through to first stoping ore in the December 2025 quarter. ... The early delivery of Nugent ore represents a key milestone in the ramp-up of Hillgrove’s copper production profile, providing additional operational flexibility as the company prepares for increased mill throughp
All amounts are in United States dollars, unless otherwise stated. TORONTO, June 23, 2025 (GLOBE NEWSWIRE) -- Alamos Gold Inc. ( TSX:AGI; NYSE:AGI ) (“Alamos” or the “Company”) today reported results of the Base Case Life of Mine Plan (“Base Case LOM Plan”) completed on the Island Gold District operation, located in Ontario, Canada. The Base Case LOM Plan integrates Island Gold and Magino as one consolidated long-life operation that is expected to become one of the largest, lowest-cost, and most profitable gold mines in Canada. An Expansion Study is expected to be released in the fourth quarter of 2025 detailing the significant upside potential within the Island Gold District beyond the Base Case LOM Plan. The Base Case LOM Plan has been updated to reflect the current costing
June 20, 2025
June 20, 2025 (Source: Gemfields Group) LONDON , 20 JUNE 2025 Gemfields hereby provides a market update regarding its three principal subsidiaries. Montepuez Ruby Mine (“MRM”) Construction of MRM’s second processing plant (or “PP2”), designed to triple MRM’s ore processing capacity from 200tph to 600tph, is 95% complete and materially on budget. PP2 is now expected to produce its first rubies during August 2025 courtesy of the plant’s core components. Final completion of PP2, including the tailings belt conveyor and decanter centrifuge, is now expected to occur during September 2025. Final completion has been delayed as a result of, inter alia: a. difficulties in obtaining the requisite work permits, particularly in relation to specialist electrical component installation,
June 16, 2025
TORONTO, June 16, 2025 (GLOBE NEWSWIRE) -- Blue Moon Metals Inc. (“ Blue Moon ” or the “ Company ”) ( TSXV: MOON ; OTCQX: BMOOF ), is pleased to announce that the company has commenced underground construction on the Nussir Mine completing the first blast on the access portal on June 12, 2025; ahead of schedule. Nussir’s mining contractor, Leonhard Nilsen & Sonner AS (“ LNS ”) will extend the decline approximately 2,500 meters providing a platform for further underground exploration. The exploration work to be completed over the next year will provide key engineering inputs and lead to a final investment decision in 2026. Christian Kargl-Simard, Blue Moon’s CEO states: “This key milestone marks the start of the next chapter in the exciting Nussir story and brings us one step closer to p
June 16, 2025 (Source: Vale) Rio de Janeiro, June 16th, 2025. Vale announces that it has obtained the Preliminary Environmental License for the Bacaba copper project, located in Canaã dos Carajás, Pará, Brazil. The Bacaba project is designed to extend the life of the Sossego Mining Complex , contributing with an average annual copper production of approximately 50 ktpa over an 8-year mine life. Approximately US$ 290 million will be invested during the project’s implementation phase and the production startup is planned for the first half of 2028 . This is the first in a series of copper projects that Vale intends to develop in the Carajás mineral province, as part of its strategic objective to double its copper production capacity over the next decade
June 12, 2025
June 12, 2025 (Source: Meeka Metals Ltd.) Ore is being fed into the processing plant and commissioning is underway at the Murchison Gold Project (“Murchison”). • The commissioning team is on site and working with the construction and processing teams to commission the processing plant. • Dry commissioning (system and equipment testing) has progressed successfully and ore is now being fed into the plant
June 11, 2025
June 12, 2025 ( ACCESS Newswire) - Cerrado Gold Inc. [TSX.V:CERT][OTCQX:CRDOF][FRA:BAI0] (" Cerrado " or the " Company ") is pleased to provide an update on the development of the Company's inaugural underground operation commencing underneath the high-grade Paloma pit at its Minera Don Nicolas Mine in Argentina ("MDN"). Earlier this week, the Company completed the initial blast to begin construction of the underground portal and progress the development of the underground mine over the coming months. The initial decline will be driven through the ore body and will provide nominal feed to the carbon in leach ("CIL") plant. Production from the underground is expected to ramp-up to reach steady state production by October this year. Additionally, the Company has now m
June 10, 2025
Vancouver, British Columbia--(Newsfile Corp. - June 10, 2025) - ESGold Corp. (CSE: ESAU) (OTCQB: ESAUF) (FSE: Z7D) ("ESGold" or the "Company") , a fully permitted, pre-production gold and silver company, is pleased to provide a corporate update on construction progress, technical milestones, and the next phase of its growth strategy at the Montauban Project in Quebec. With construction now advancing steadily on-site, the Company confirms the successful installation of the Humphrey Spirals—a core component of the gravity separation circuit that will be used to process historical tailings and recover gold, silver, and mica concentrate at Montauban. This milestone establishes the foundation for the plant's initial production throughput, with equipment capable of supporting up to 1,000 ton
June 6, 2025
WASHINGTON, June 6 (Reuters) - The U.S. Interior Department approved a plan by Signal Peak Energy to expand coal mining, providing exports for Japan and South Korea, the agency said on Friday, as it responded to President Donald Trump's energy-emergency directives. The approval authorizes the Montana-based coal company to recover 22.8 million metric tons of federal coal and 34.5 million tons of adjacent non-federal coal and extend the life of the Bull Mountains mine by nine years. Interior Secretary Doug Burgum, who is also co-chair of Trump's Energy Dominance Council, said unlocking more federal coal enables the U.S. to bolster ties with allies abroad. "President Trump’s leadership in declaring a national energy emergency is allowing us to act decisively, cut bureaucratic delays