Mining Intelligence and News
Australia

Northparkes Mine

Click for more information

Categories

Summary

Mine TypeOpen Pit & Underground
StatusActive
Commodities
  • Copper
  • Gold
  • Silver
Mining Method
  • Truck & Shovel / Loader
  • Sub-level caving
  • Block caving
Shaft Depth 520 m
Production Start1993
Mine Life2032
SnapshotNorthparkes is an underground and open-pit copper-gold mine. The mining methods at Northparkes include underground extraction of low-grade, large rock masses with suitable caving properties. While open-pit mining was utilised in the past, it continues on several smaller deposits. The onsite processing plant produces a copper-gold-silver concentrate, which is then transported by truck and rail to the Port of Newcastle for shipment to international customers.

In June 2024, the Board approved the progression of the E48 sub-level cave at Northparkes to the Pre-Feasibility Study stage. This development is projected to extend the life of the Northparkes mine until 2054.

During FY25, the E48 L2 Sublevel Cave Pre-Feasibility Study was completed. The SLC leverages existing underground infrastructure, reducing capital costs and improving operational efficiency. The Project moved to execution phase, with production targeted for the first half of FY26.

Owners

SourceSource
CompanyInterestOwnership
Sumitomo Corp. 6.7 % Indirect
Sumitomo Metal Mining Co., Ltd 13.3 % Indirect
Evolution Mining Ltd. 80 % Indirect
Evolution Mining (Northparkes) Pty Ltd. (operator) 80 % Direct
Evolution Mining Ltd. has 80% interest in Northparkes operation, joining the Sumitomo Group (20% interest) in a longstanding joint venture.

Operator: Evolution Mining (Northparkes) Pty Ltd operating as Northparkes Mining Services Pty Ltd.

Contractors

ContractorContractDescriptionRef. DateSource
unawarded or unknown Power supply Grid power supplied to the mine by 132kV transmission line. Jun 30, 2025

Deposit type

  • Breccia pipe / Stockwork
  • Porphyry
  • Vein / narrow vein

Summary:

The Northparkes deposits occur within the Ordovician Goonumbla Volcanics of the Goonumbla Volcanic Complex and Wombin Volcanics. The Goonumbla Volcanics form part of the Junee-Narromine Volcanic Belt of the Lachlan Orogen and consist of a folded sequence of trachyandesitic to trachytic volcanics and volcaniclastic sediments that are interpreted to have been deposited in a submarine environment.

The Goonumbla Volcanics at Northparkes have undergone little deformation, with gentle to moderate bedding dips as a result of regional folding. The dominant structure observed to date in the Northparkes area is the Altona Fault, an east-dipping thrust fault, which truncates the top of E48 and GRP314 and is known to extend from east of E26 north through E27.

Resources at Northparkes are associated with alkalic porphyry copper-gold deposits. Copper and gold mineralisation occurs as quartz-sulphide veins, breccia-fill and disseminations developed in and around clusters of pencil-shaped magmatic intrusions of quartz monzonite composition. Copper occurs as bornite (Cu5FeS4 ) and chalcopyrite (CuFeS2 ), while gold occurs as microscopic native gold grains within and around the copper sulphides.

The porphyries form narrow, typically less than 50 m in diameter, but vertically extensive (greater than 1,000 m) pipes. Mineralisation extends from the porphyries into their host lithology. The life of mine plan is focused on five porphyries, referred to as E26, E48, E22, E31 and GRP314; in addition to these zones numerous other mineralised porphyries exist across the district. The deposits are hosted within both the Goonumbla and Wombin Volcanics, with mineralisation related intrusive rocks effectively forming part of the latter.

Sulphide mineralisation occurs in quartz stockwork veins, as disseminations and fracture coatings. Highest grades are generally associated with the most intense stockwork veining. Sulphide species in the systems are zoned from bornite-dominant cores, centred on the quartz monzonite porphyries, outwards through a chalcopyrite-dominant zone to distal pyrite. As the copper grade increases (approximately > 1.2 per cent copper), the content of covellite, digenite and chalcocite associated with the bornite mineralisation also increases. Gold normally occurs as fine inclusions within the bornite; due to the intimate relationship with bornite, visible gold tends to occur within the highest-grade zones of the central portion of the deposit. A small portion of gold mineralisation does not appear to be directly associated with copper sulphide minerals. Silver is associated with copper sulphide minerals and is present in solid solution and as inclusions of silver-bearing tellurides and electrum. Copper-to-gold ratios differ between the different deposits and within individual deposits.

All of the Northparkes deposits are cross-cut by late faults/veins filled with quartz carbonate and minor gypsum, anhydrite, pyrite, tennantite chalcopyrite, sphalerite and galena, the associated sericite alteration can extend up to 10 m from the faults. Tennantite, which contributes arsenic to the final copper concentrate, is present in higher concentrations in the E48 deposit.

Oxide mineralisation blankets were well developed over the E22 and E27 deposits. The upper blanket was gold-rich and copper-poor. The lower blanket was enriched in copper by supergene processes. The dominant copper oxide minerals at E22 and E27 were copper carbonates (malachite and azurite) and phosphates (pseudomalachite and libethenite) with lesser chalcocite, native copper, cuprite and chrysocolla. A gold-poor, less well developed, supergene copper blanket was also developed over the E26 deposit. At E26 the oxide copper minerals included atacamite, clinoatacamite and sampleite, in addition to those copper minerals observed in E22 and E27.

The Northparkes deposits are typical porphyry copper systems, in that the mineralisation and alteration are zoned around multiphase quartz monzonite porphyries. As described by Pacey et al (2019) mineralization was caused by the forcible, periodic escape of low-viscosity, crystal and volatile-rich magmas. These exploited pre-existing structural intersections and focused the discharge of large quantities of magmatic fluids from the underlying chamber. The fluids circulated in intricate fracture networks to produce K-feldspar-sulphide veinlets and quartz sulphide stockwork veins, surrounded by K-feldspar–dominated alteration. Ore grades are exclusively located within the potassic alteration zones, although some have been sericitically overprinted.

Reserves at December 31, 2024

Ore Reserve cut-off grades: for OP - 0.34% - 0.50% CuEq, for UG - 0.32 - 0.58% CuEq.

Mineral Resources are reported inclusive of Mineral Reserves.
CategoryTonnage CommodityGradeContained Metal
Probable 90 Mt Copper 0.54 % 487.5 kt
Probable 90 Mt Gold 0.27 g/t 0.8 M oz
Proven & Probable 101 Mt Copper 0.52 % 525 kt
Proven & Probable 101 Mt Gold 0.28 g/t 0.9 M oz
Measured 225 Mt Copper 0.53 % 1,225 kt
Measured 225 Mt Gold 0.26 g/t 2 M oz
Indicated 325 Mt Copper 0.49 % 1,625 kt
Indicated 325 Mt Gold 0.14 g/t 1.5 M oz
Inferred 50 Mt Copper 0.46 % 225 kt
Inferred 50 Mt Gold 0.16 g/t 0.3 M oz

Mining Methods

  • Truck & Shovel / Loader
  • Sub-level caving
  • Block caving

Summary:

Northparkes is an underground and open pit operation which include block-caving and sub-level caving mining methods.

Underground Operations
As of 2025, ore is mined from E26LN and, until recently, E48L1 as well. Block caving relies on gravity and natural rock stresses to fragment and recover the ore, using minimal explosives.

* E48
- First lift (E48L1) completed December 2023;
- Sub level cave (SLC) due to be executed from FY25, benefitting from existing infrastructure;
- First fully automated underground mining operation.

* E26
- E26 mining areas comprised of L1, L2, L1N block caves and the E26SLC;
- Mining is focused on E26L1N block cave (commenced 2022) and E26SLC (commenced 2016);
- E26 L1N block cave expected to operate thru 2032;
- E26SLC consists of 6 sub levels, 4 mined to date.

Block cave mining accounts for the majority of ore production at Northparkes, with minor contributions from surface stockpile reclamation and open pit mining. Preproduction mining development work consists of establishing two working levels, the undercut level and extraction level, at the base of each ore block, as well as the development to support the associated material handling system. Northparkes has developed its own unique extraction level layout that locates the material handling system, including crusher, to the side of the extraction level, thereby alleviating the need to construct a third level dedicated to haulage. Similarly, it has established the extraction level as the primary ventilation level, thereby eliminating development to support mine ventilation. The undercut level, which is used to initiate caving, is 14 - 20 m vertically above the extraction level, the height being dependent on the undercutting method. Undercutting, which involves sequential firings of overlapping fans of blastholes to create the initial void for caving, is the rate controlling step for production ramp-up, controlling both the rate of undercutting ore and the start of production from drawpoints.

The Northparkes rock mass, including the E48 and E26 deposits, is a highly jointed rock mass with fracture frequencies of between three and 20/m and fracture density that increases with copper grade.

Mine access for all personnel and equipment is provided by surface portal and decline. The decline has a standard 5 m wide by 5.5 m high arched profile. The hoisting shaft represents the second means of egress and the ore skips can be fitted with a man-riding cage in the event that personnel cannot egress the mine via the decline. The mining process involves recovery of broken rock from the drawpoints by 14 t capacity electric LHDs, which tram the ore to a primary crushing station, consisting of plate feeder and jaw gyratory crusher, located on the margin of the extraction level. Typically, four to five LHDs operate on a continuous basis. E48 Lift 1 is highly automated, utilising driverless loaders. Crushed ore is fed onto high-speed inclined conveyors via an ore pass that also provides storage capacity. Ore is conveyed to the underground loading station, which consists of three ore passes feeding the hoisting system. The hoisting system consists of a ground mounted friction winder with integrated drum and rotor, servicing two 18 t payload skips in counterbalance, running on rope guides in the 6 m diameter concrete lined shaft. Hoisted ore is transferred via an overland conveyor to crushing cicuit.

Northparkes has developed a comprehensive cave management system based on its experiences with operating the E26 block caves. These management systems are designed to manage the specific catastrophic safety risks particular to block caves; namely airblast, surface subsidence and inrush and large-scale rock falls. The system is also designed to support maximising reserve recovery and optimising mine production. The system is based on a large number of monitoring systems, including real-time microseismic event monitoring, open hole surveys using probes and video cameras, time domain reflectometers installed in grouted boreholes, convergence monitoring using extensometers and manual measurements of mine openings on the extraction level and in key underground infrastructure, drawpoint fragmentation and geology mapping, drawpoint grade sampling, subsidence zone volume surveys and water inflow measurements.

The mine ventilation system consists of two primary exhaust shafts (E26 and E48) each with two fans mounted on surface above a system of vertical and lateral return airways. The primary air intakes are the main decline, the hoisting shaft and E48 intake shaft. The ventilation system typically operates at airflows of 600 - 650 m3 per second, which are shared across the various work areas.

Underground operations in 2024 included the mining of the E26 L1N block cave, E26 SLC and the development of the E48 SLC.

Underground mining activities are undertaken in the E26 ore body. The E26 L1N mine is operated as a block cave as the primary method of resource extraction. Block caving is an underground hard rock mining method that involves undermining an ore body and allowing it to progressively collapse under its own weight. The E26 SLC mine is a sublevel caving operation involving construction of the sub level horizon followed by retreat drill and blast of that horizon, with the material above allowed to freely cave to fill the opened voids.

The E26 SLC project commenced construction in April 2015 and went into production in 2016. The mine design aimed to extract a remnant wedge of high-grade material adjacent to the E26 Lift 2 block cave. The operations at E26 SLC had ceased in 2021, having completed production from the first four levels at approximately 20m vertical spacing. The remaining two levels were deferred due to less favourable economics. The development of the remaining levels commenced in 2023 with 25m vertical spacings.

Production has been completed from level 5, with level 6 coming online early in 2025. Production in the SLC is expected to continue until October 2025.

Mining development is planned to continue in 2025 for the purpose of accessing the E48 SLC ore body, with development for the E22 Block Cave likely to be delayed until future years.

Open cut
The semi-automated driver-less loaders are operated from surface, where the operator controls the equipment to load ore from the drawpoint, then engages automation for the loader to tram and dump the ore.

Throughout 2024, mining at the E31 Project continued, providing a reliable, additional source of highgrade ore to the Northparkes operation. Approximately 8.5Mt of material were mined from the two pits (E31 and E31N) in the year including different types of ore and waste.

Drill and blast activities were undertaken throughout the year, with blast days generally limited to once a week.

Heavy Mobile Equipment

HME TypeModelQuantityStatusRef. DateSource
Load-Haul-Dump (LHD) - AV Sandvik LH514 1 Existing Dec 18, 2019
Load-Haul-Dump (LHD) - AV Sandvik LH514 1 Required Jul 5, 2024
Load-Haul-Dump (LHD) - EAV Sandvik LH514E 5 Existing Dec 18, 2019
EV - Electric
AV - Autonomous

Comminution

Crushers and Mills

TypeModelSizePowerQuantity
Gyratory crusher ThyssenKrupp BK 63-75 3
Pebble crusher 3
SAG mill 4.9 MW 1
SAG mill 2.9 MW 1
Ball mill 1.6 MW 1
Ball mill 2.9 MW 1
Ball mill 4.9 MW 1
Ball mill 1.3 MW 1

Summary:

Ore is fed to the plant from two sources; via the underground operations and the winder, or from open cut material via a surface crushers. New surface secondary crushing and screening facility installed with Sandvik crushers.

Underground Crushing
The first BK 63-75 crusher was commissioned underground at Northparkes in 2003 followed by a second installation in 2009.

2019 - Northparkes is installing a third BK 63-75 at the new E26L1N block cavern underground crushing station.

The first two crushers installed are of a single mouth design with the latest crusher being a double mouth design.

The latest crusher is noteworthy as the world’s first “double-mouth” jaw-gyratory crusher, developed by thyssenkrupp Industrial Solutions in consultation with Northparkes to meet its specific operating objectives. It is based on the proven BK 63-75 design but has a new, patented, spider to give the opportunity to feed the crusher from both sides – the double mouth jaw configuration – thus removing the need for a primary crusher feed (buffer) hopper and primary apron feeder.

Grinding
The comminution process consists of two parallel grinding modules and a single line flotation plant consisting of a SAG, ball and tertiary mills:

•Module 1: 2.9MW SAG mill with a pebble crushing circuit followed by a 2.9MW primary ball mill and 1.3MW tertiary ball mill; throughput rates vary between 280tph and 430tph depending on feed size, with a final product grindsize (P80) of between 90-140um; and

• Module 2: 4.9MW SAG mill with two pebble crushers followed by a 4.9MW primary ball mill and a 1.6MW tertiary ball mill; throughput rates vary between 450tph and 680tph depending on SAG mill feed size, with a final product grindsize of between 100-160um.

Processing

  • Jameson Cell Flotation
  • Crush & Screen plant
  • Flotation
  • Dewatering

Summary:

The Northparkes processing plant is designed for sulphide ore and includes crushing, stockpiles, grinding mills, froth flotation area and storage. The sulphide flotation process is used to produce a concentrate containing copper, gold and silver. Concentrate is trucked/railed to Port of Newcastle and shipped to international clients.

Ore processing includes several defined stages that include crushing, grinding, flotation and dewatering. Ore is sourced from either underground mines, surface stockpiles or open pits, where it is first primary crushed, followed by passing through a secondary and tertiary crushing circuit before being stockpiled into two separate stockpiles. From the stockpiles, material is fed to the grinding circuit, compromising of two parallel modules (Mod 1 and Mod 2), each incorporating a Semi Autogenous Grinding (SAG) mill, oversize pebble crushing, two stages of ball milling, flotation (rougher-scavenger with cleaning stage) and thickeners for concentrate and tails streams.

From grinding, the material flows through a single line flotation circuit; initially through a series of rougher/scavenger flotation cells, before entering the cleaner circuit, comprised of Jameson Cells and mechanical cleaner-scavengers. Copper and Gold bearing sulfide minerals are recovered using Hostaflot 26293 as the primary flotation collector and Flotanol 16319 as the frother as well as Sodium.

Hydrosulphide (NaHS) as a sulphidizing agent. Concentrate produced from the flotation circuit is thickened and filtered to produce a final concentrate, with a moisture content of 8-10%.

Air and agitation to produce bubbles in combination with a suite of regents, to enable attachment of particles (minerals) are captured and recovered in the flotation process to produce a sulphide-rich concentrate containing Copper and Gold bearing minerals. After flotation, the concentrate is first thickened through thickeners and filtered through ceramic disc filters to produce a low moisture concentrate ready for loading and transportation to the port.

The recent expansion project comprised of: (1) the installation of a closed loop secondary & tertiary crushing circuit to replace the existing open circuit secondary crusher; (2) upgrading of the feed conveyors, discharge screens, hoppers, cyclone clusters and pumps; and (3) Relocation of existing pre flotation cell, installing a new flotation cell and refurbishing the cleaner scavenger cells.

Commissioning of the new secondary and tertiary crushing facility was completed in 2021 allowing the concentrator to achieve a nominal throughput rate of 7.6Mtpa.

The tailings component is pumped from the final flotation stage to a tails thickener for dewatering followed by additional pumping to the tailing’s storage facilities.

Recoveries & Grades:

CommodityParameter202320222021202020192018201720162015
Copper Recovery Rate, % 83.38282.885.388.487.687.78888
Copper Head Grade, % 0.470.540.630.650.730.780.890.97
Gold Recovery Rate, % 70.767.769.172.676.477.975.37575
Gold Head Grade, g/t 0.130.170.180.160.210.230.260.32
Copper Concentrate Grade, %

Pipelines and Water Supply

TypeMaterialDiameterLengthDescription
Water pipeline 18 km

Water usage

Parameter202520242022202120202019
Surface water 1,215 ML
Mine dewatering water 56 ML525 ML
Groundwater 477 ML
Recycled water 3,980 ML4,038 ML4,563 ML4,004 ML2,392 ML2,872 ML
Water use efficiency 0.24 kL/t0.35 kL/t
Precipitation water 210 ML
Third-party water 1,727 ML
Fresh water 2,025 ML2,684 ML2,998 ML3,009 ML

Summary:

Northparkes sources water from numerous locations including imported water from various licences.

Water recycled from the on-site ore processing facility and tailings dam reclamation system is collected through existing on-site infrastructure.

Effective water management is crucial to the long-term success of Northparkes operations as it is essential in the processing of ore through the concentrator to produce copper concentrate. The water management system aims to collect efficiently and economically, store and re-use water onsite to minimise external water supply inputs and supplement supply during periods of high consumption.

Commodity Production

The data up to 2023 reflects the mine's operational performance for the calendar year from January 1 to December 31. In December 2023, following a change in ownership, Evolution acquired an 80% stake in the Northparkes copper-gold mine from CMOC Group Limited ('CMOC'). As a result, the company shifted its reporting period to a financial year running from July 1 to June 30. Consequently, the mine’s 2024 performance indicators overlap with the 2023 data for the period between July 1, 2023 and December 31, 2023.
CommodityProductUnits20252024202320222021202020192018201720162015
Copper Payable metal t 35,60637,32733,440
Gold Payable metal koz 613925
Gold Equivalent Payable metal oz 179,650
Silver Payable metal oz 308,710
Copper Concentrate kt 136118108108121125132137152
Copper Metal t 28,38329,41833,74635,73939,93143,64145,93649,955
Gold Metal koz 2025262533353647

Operational metrics

Metrics20252024202320222021202020192018201720162015
Annual milling capacity 5.8 Mt7.6 Mt7.6 Mt7.6 Mt7.6 Mt6.5 Mt6.5 Mt6.5 Mt
Waste 1,107,943 t4,212,644 t3,108,956 t894,872 t
Ore tonnes mined 8,477,339 t6,777,712 t6.95 Mt7.62 Mt5.37 Mt6 Mt6.22 Mt6.52 Mt6.46 Mt6.07 Mt
Total tonnes mined 9,585,282 t13,417,629 t
Tonnes milled 7,289,635 t7,014,348 t7.28 Mt7.6 Mt6.84 Mt6.49 Mt6.42 Mt6.48 Mt6.51 Mt6.17 Mt6.35 Mt
Waste UG 10,374 t196,450 t158,661 t80,329 t14,004 t64,652 t

Production Costs

Commodity2025201920182017
Credits (by-product) Gold -8,351 / oz  AUD
All-in sustaining costs (sold) Gold -2,514 / oz **  AUD
All-in sustaining costs (AISC) Copper 1.15 / lb **  USD
C1 cash costs (sold) Gold -3,045 / oz **  AUD
C1 cash costs Gold -2,765 / oz **  AUD
All-in costs Gold -1,687 / oz **  AUD
C1 cash costs Copper 1.08 / lb **  USD 0.92 / lb **  USD
^ Guidance / Forecast.
** Net of By-Product.

Mine Financials

Units2025202220212020201920182017
Sustaining costs M AUD 21  
Growth Capital M AUD 41.5  
Capital expenditures M AUD 62.5  
Revenue M 633  AUD1,616  RMB2,066  RMB1,795  RMB 1,653  RMB 1,823  RMB 2,080  RMB
Operating Income M 312.8  RMB 393.8  RMB
Pre-tax Income M 310.9  RMB 406.4  RMB
After-tax Income M 245.1  RMB 245.8  RMB
EBITDA M 313.6  AUD
Operating Cash Flow M 373.7  AUD

Personnel

Mine Management

Job TitleNameProfileRef. Date
Commercial Manager Glenn Pearson LinkedIn Oct 30, 2025
General Manager Operations Rob Cunningham LinkedIn Oct 30, 2025
Operations Manager Johan Ferreira LinkedIn Oct 30, 2025
Processing Manager Mitch Garside LinkedIn Oct 30, 2025
Superintendent Logistics Gabe (Rosser) Albert LinkedIn Oct 30, 2025
Technical Services Manager Sergio Melloni LinkedIn Oct 30, 2025
Technical Services Superintendent Riek Muller LinkedIn Oct 30, 2025

Workforce

EmployeesContractorsTotal WorkforceYear
438 179 617 2025
430 1,379 1,809 2024
380 579 959 2023
424 2022
431 2021
469 2020
428 2019
329 2018
313 2017
353 2016
324 2015
324 2014

Aerial view: