
Anglo American plc. through its subsidiary Rustenburg Platinum Mines owns 65.36% of the Amandelbult complex.
As part of its portfolio simplification, Anglo American plc. will demerge Anglo American Platinum, allowing it to operate as an independent and resilient business. The demerger is expected to be completed in June 2025.
Contractor | Contract | Description | Ref. Date | Source |
Eskom Holdings SOC Ltd
|
Power supply
|
Electricity to the complex is supplied by Eskom via an electricity distribution network.
|
May 31, 2023
|
|
Summary:
Amplats’ Mineral Resources of Platinum Group Metals (PGM) occur exclusively within southern Africa and are hosted by two distinct layered intrusions: the Bushveld Complex in South Africa and the Great Dyke in Zimbabwe.
The mines Tumela and Dishaba are forms part of the Amandelbult section and fully developed situated on the north-western limb of the Bushveld Complex.The mining occurs on both the Merensky Reef and the UG2 Reef horizons.
Bushveld Complex
Formed over two billion years ago as a result of multiple injections of magma into the earth’s crust many kilometres below the surface, the Bushveld Complex is geologically unique due to its size, uniformity of its layering and extent of known mineral content. This saucer-shaped intrusion is over 350km wide, 250km long and up to 12km thick. Over time, the rim of the intrusion has been exposed by erosion, revealing three major separate segments known as the Western, Eastern and Northern Limbs. The Western Limb is split into two lobes (north-western and south-western) by the Pilanesberg Complex, a remnant of an alkaline volcanic plug that intruded into the Bushveld Complex about 1.2 billion years ago. The north/east trending Steelpoort fault divides the Eastern Limb into two lobes: north-eastern and south-eastern. The exposed segments exhibit layering of pyroxenites, norites, gabbros, anorthosites and chromitites across the entire extent of the complex.
The Bushveld Complex comprises three main suites, namely the Rooiberg Group, Lebowa Granite Suite and Rustenburg Layered Suite. The Rustenburg Layered Suite comprises four major subdivisions: the upper zone, main zone, critical zone and lower zone. Economic concentrations of PGMs occur mainly in three distinct units within the critical zone: Merensky Reef; Upper Group 2 (UG2) chromitite; and Platreef. The Merensky Reef and UG2 Reef occur along the Eastern (EL) and Western (WL) Limbs of the complex, while the Platreef is restricted to the eastern edge of the Northern Limb (NL). The UG2 and Merensky Reefs are extracted at Amandelbult, Mototolo, Twickenham and Modikwa while the Platreef is extracted at Mogalakwena.
The Merensky and UG2 Reefs are narrow tabular orebodies that extend laterally over hundreds of square kilometres, resulting in extensive mineralisation.
The Merensky Reef
The Merensky Reef has been the principal source of PGMs since it was first mined in 1925. The reef contains economically important PGMs and base metal sulphide mineralisation.
It is extensively developed in both the EL and WL of the Bushveld Complex. The reef typically consists of a pegmatoidal feldspathic pyroxenite layer, bound at the top and bottom by thin chromitite layers (stringers) that range from 5mm to 20mm in thickness. Mineralisation of the reef generally occurs within the pegmatoidal feldspathic pyroxenite and, to a limited extent, in the hanging wall and footwall, with the highest PGM concentration peaking in the chromitite stringers.
In the WL, the Merensky Reef dips in an arc ranging from 18º to 27º south-easterly direction in the Amandelbult area and at 9º to 12º northerly direction in the Rustenburg area. It has a variable reef thickness ranging from 1cm (Contact Reef facies) to >2m, over large areas. At Amandelbult complex in particular, the reef comprises up to five different facies. Each facies type exhibits unique geomorphological, geochemical and mineralisation characteristics and plays a fundamental role in geozone delineations and Resource and Reserves widths. In the EL, the Merensky Reef is slightly thicker and dips at 8º to 18º in a south-westerly direction.
The UG2 Reef
With the depletion of shallow Merensky Mineral Resources, the UG2 Reef has grown steadily in importance to the point where it now accounts for most of the PGM-bearing ore processed in South Africa. The UG2 Reef, which is consistently developed throughout the EL and WL, is rich in chromitite, with lower gold and base metal but slightly higher rhodium grades compared to the Merensky Reef.
The UG2 Reef occurs vertically below the Merensky Reef and the separation distance varies between 12m and 150m in the WL and averages at 350m to 400m in the EL. The UG2 Reef normally comprises a 0.6m to 1.0m main chromitite layer overlain by three to five chromitite layers (UG2 leaders) varying in thickness from 5cm to 30cm, separated by feldspathic pyroxenite. The immediate footwall of the UG2 is usually a pegmatoidal feldspathic pyroxenite, which varies in thickness from a few centimetres to over 1m. The separation distances between these UG2 leader chromitite layers and the UG2 main layer has important implications for geotechnical considerations for mining across the Bushveld Complex.
The UG2 Reef, which is consistently developed throughout the EL and WL, is rich in chromitite, but with lower gold and base metal content compared to Merensky Reef. In the WL, the UG2 Reef occurs between 12m and 150m vertically below the Merensky Reef and dips at 18º to 27º in a south-easterly direction (Amandelbult area). In the EL, the reef occurs between 120m and 400m vertically below the Merensky Reef and dips at 8º to 18º in a south- westerly direction.
In the WL, the UG2 normally comprises a 0.6m to 1.0m main chromitite band overlain by three chromitite bands (UG2 leaders) varying in thickness from 5cm to 30cm, separated by feldspathic pyroxenite. The immediate footwall of the UG2 is usually a pegmatoidal feldspathic pyroxenite, which varies in thickness from a few centimetres to over 1m. The separation distances between these UG2 leader chromitite bands and the UG2 main band has important implications for geotechnical considerations for mining.
In the EL, the UG2 normally comprises a main chromitite band varying in thickness from 0.3m to 1.0m, overlain by three or up to four chromitite stringers varying in thickness from 2mm to 1cm. The immediate footwall of the UG2 is usually a pegmatoidal feldspathic pyroxenite, which varies in thickness from a few centimetres to over 1m. The separation distances between these UG2 hanging wall stringers has important implications for geotechnical considerations for mining.
In the EL south of the Steelpoort fault, UG2 chromitite is an amalgamation of UG2 main chromitite with the leader chromitite unit, the two usually indistinguishable but may be separated based on their Pt/Pd ratios varying in thickness from 0.60m to 2.25m (averaging 1.20m). This is overlain by a poikilitic feldspathic pyroxenite parting varying in thickness from millimetres to 15m and averaging 1m. This parting is overlain by three chromitite bands (up to 20cm), separated by poikilitic feldspathic pyroxenite and pegmatoidal pyroxenites commonly referred to as the ‘triplets’ with an average thickness of 80cm.
Reserves at December 31, 2024
Category | Tonnage | Commodity | Grade | Contained Metal |
Proven
|
68.1 Mt
|
4E (Pt, Pd, Rh, Au)
|
4.57 g/t
|
10 M oz
|
Probable
|
20.9 Mt
|
4E (Pt, Pd, Rh, Au)
|
4.47 g/t
|
3 M oz
|
Proven & Probable
|
88.8 Mt
|
4E (Pt, Pd, Rh, Au)
|
4.52 g/t
|
12.9 M oz
|
Measured
|
108.8 Mt
|
4E (Pt, Pd, Rh, Au)
|
5.8 g/t
|
20.3 M oz
|
Indicated
|
150.4 Mt
|
4E (Pt, Pd, Rh, Au)
|
6.1 g/t
|
29.5 M oz
|
Measured & Indicated
|
259.2 Mt
|
4E (Pt, Pd, Rh, Au)
|
5.98 g/t
|
49.8 M oz
|
Inferred
|
114.9 Mt
|
4E (Pt, Pd, Rh, Au)
|
6.33 g/t
|
23.4 M oz
|
Total Resource
|
374.1 Mt
|
4E (Pt, Pd, Rh, Au)
|
6.08 g/t
|
73.1 M oz
|
Mining Methods
- Breast stoping with strike pillars
- ULP / XLP
Summary:
The Amandelbult complex has two mines: Tumela and Dishaba. The current working mine infrastructure has five vertical and seven decline shaft systems to transport rock, people and material, mining on the Merensky and UG2 Reef horizons. The mining method is a combination of conventional scattered breast mining with strike pillars, mechanised mining areas and opencast. The operating depth for current workings runs from surface to 1.3km below surface.
In 2024 there was no mining of Merensky Reef at Dishaba and Tumela.
Conventional scattered breast mining is preceded by haulage development below reef, parallel to strike. Access to the reef horizon is developed by means of south or north crosscuts. On-reef true dip raises or winzes connect to cross-cuts on different levels by means of step overs and travelling ways. The ore passes are generally done by inverse drilling (from the reef horizon down to the crosscut). Modernised equipment is being rolled out on the stoping horizon to address safety and efficiency concerns, including the introduction of cycle mining, split panels utilising throw blasting and water-jet cleaning to eliminate the use of scraper winches.
The ore is scraped into stope ore passes and then hauled (footwall haulages) by battery powered locomotives to the main hoisting shafts. From surface the ore is transported to the concentrator by rail.
Mechanised Mining At Amandelbult
The Amandelbult Mine Complex employs a labour-intensive conventional mining methodology for the mining of its narrow tabular ore body. In 2021 Anglo American Platinum commenced with the implementation of a portfolio of mechanised mining projects as volume replacements for the depleting conventional / modernised investment centres. The development of the mechanised mining knowledge base will be leveraging technical and operational learnings from the Tumela 15E Mechanised project together with industry best practice.
Dishaba East Mechanised Project
The Dishaba East Mechanisation project is on the north eastern boundary of the AMB. Two Option have been identified where the surface area can be located:
* Existing 62E Footwall area;
* Haakdoorndrift surface area.
The underground mine area consists of an Upper and Lower area. The Upper area will be accessed from surface and the Lower area will be accessed from the existing underground infrastructure at Dishaba 2 Shaft.
The existing 62E Footwall is the preferred alternative as the area is already disturbed and it is on an established footprint. The footprint in this area is larger than if it would be position at the Haakdoorndrift area as the infrastructure needs to be positioned in between existing established buildings and structures.
Mechanised Mining At Tumela
The Amandelbult Mine Complex employs a labour-intensive conventional mining methodology for the mining of its narrow tabular ore body. In 2021 Anglo American Platinum commenced with the implementation of a portfolio of mechanised mining projects as volume replacements for the depleting conventional / modernised investment centres. The development of the mechanised mining knowledge base will be leveraging technical and operational learnings from the Tumela 15E Mechanised project together with industry best practice.
The mechanised mining is an underground mining method designed to exploit narrow reef orebodies (1.2m to 1.7m width) with a dip less than 22°. It maximises reef extraction by placing the primary development (main infrastructure) on reef. A constant production is achieved by coordinating XLP and low profile (LP) equipment to continuously feed the conveyor belt system.
The mechanisation projects consist of the following four major Capital Projects and associated infrastructure:
• Middellaagte Upper & Middellaagte Lower;
• Tumela 1 Sub Shaft;
• Tumela 15E Extension.
The Tumela 1 Sub Shaft Project is a mechanised operation below the current conventional mine. The Project is a volume replacement for the depleting traditional and modernised production areas within Tumela 1 Lower Shaft. The project is brownfield and will leverage the existing infrastructure at Tumela 1 to support the underground operation. The current Tumela hoisting infrastructure will be used to access the project area. The existing rock hoisting infrastructure is earmarked to support development and production from Tumela 1 Sub Shaft operation. New surface infrastructure includes a personnel & material shaft from surface to 16 Level and ventilation shafts.
Tumela 15E DD project was planned as a fully trackless operation using narrow reef equipment (NRE) and low-profile equipment (LP). Reliability and performance issues on the NRE fleet resulted in lower productivity and higher cost. The year-on-year improvements were in line with plan, but unsustainable in current market conditions. For this reason, it was decided to use modernised face and support drilling in the mechanised layout in 2024 to increase productivity, reduce system cost and support a faster ramp-up to production.
The Tumela 15E Extension Project is a deeper ‘extension’ of the exiting 15E dropdown project and continues the 15E Mechanisation Dropdown project that commenced in 2019. The project will primarily be supported by the existing Tumela 15E infrastructure for personnel and material. However, new surface infrastructure will be required for ventilation and rock handling to support the increase in tonnages from the current 75ktpm to more than 110ktpm.
As of 2024, Tumela 1 subshaft completed 1,436m of development against a plan of 1,262m. Excavations for the initial workshop were completed ahead of schedule. The 15 East dropdown-ventilation study was stopped due to a strategic decision to convert 15 East dropdown into a hybrid mine. Mining designs for the conversion have started.
Heavy Mobile Equipment
Fleet data has not been reported.
Comminution
Crushers and Mills
Type | Model | Size | Power | Quantity |
Ball mill
|
|
|
|
1
|
Stirred mill
|
IsaMill M10000
|
|
3000 kW
|
4
|
Ultra Fine Grind (UFG)
|
IsaMill M3000
|
|
1500 kW
|
1
|
Summary:
Mainstream inert grinding (MIG) and Ultra-fine grinding (UFG) concentrate regrind mills:
MIG - 4 x IsaMill™M10000
UFG - 1 x IsaMill™M3000
Processing
- Desliming
- Spiral concentrator / separator
- Gravity separation
- Electric furnace
- Crush & Screen plant
- Flotation
- Dewatering
Summary:
Amandelbult complex facility comprises two operational concentrators with two chrome recovery plants.
The concentrator complex is capable of processing 600 ktpm. The ore undergoes several processes, including milling and concentrating, to extract the target minerals. The concentrate is transported to off-site smelters for further refinement.
Ore mined from the reserves is processed at the AMB Concentrator before being transported to various AAP smelters for smelting and further refining at the Rustenburg Base Metals Refinery and Precious Metals Refinery. The main metal produced is platinum with other metals in the platinum group metal (PGM) suite that being chrome, rhodium, palladium, ruthenium, iridium, osmium, and including gold. Base metals produced, include copper, nickel and cobalt.
Concentrator complex
Mined ore from the shafts at RPM – Amandelbult section are hoisted to the surface and trammed separately to the two rail receiving bunkers, from where the ore is stored at the Concentrator. The refined ore is then transported by rail to the Waterval Smelter in Rustenburg for processing and further refining.
The smelter objective is to process wet concentrate to produce crushed, slowcooled, sulphur-deficient nickel-copper matte rich in platinum group metals, gold, and base metals for despatch to the Magnetic Concentration Plant at the Base Metals Refinery.
Wet concentrate is dried, then melted in electric furnaces, and excess iron sulphides are removed in the ACP converter. A slag cleaning furnace treats gangue from the converter, while a slag milling and flotation circuit treats the slag from the electric furnaces.
Wet concentrate with an average moisture content of 16-17% by mass is delivered by road in flexi-side tippers or containers, and offloaded in the concentrate-receiving shed. Slurries with a solids content of 50-60% are pumped or delivered by tanker to the Waterval Complex Concentrate Handling plant (WCCH) for dewatering.
In the flash drying process, moisture is removed from the wet concentrate, producing a dry furnace feedstock (<0.5% H2O). The energy for the process is provided by burning coal in a fluidised bed (silica sand) combustor known as a hot gas generator (HGG).
The two electric furnaces are of Hatch design, with a rated transformer capacity of 39 MVA (34 MW maximum or 30 MW nominal design), and a design operating factor of 90%. The rectangular furnaces have internal dimensions of 8.0 x 25.8 m, and the calculated power flux at nominal design is 146 kW/m². The shell is constructed from refractory bricks held together by a precision-designed tension system.
Waterval furnace matte (WFM) is tapped into matte ladles and transported by crane to one of two granulation stations. The ladle is placed on a hydraulically driven tilter that pours the matte into a granulation launder at a predetermined rate. The launder discharges above a stream of granulating water that shearquenches the matte, forming fine particles suitable for dry feeding into the ACP converter.
The slag-cleaning furnace (SCF) is a 12 m diameter round furnace, designed by Pyromet, rated at 30 MVA (23 MW). Three Söderberg electrodes, each 1 400 mm in diameter, deliver power into the bath at currents up to 80 kA. The high currents are required due to the high conductivity of the slag. The resulting high slag temperatures led to the design choice of water-cooled copper sidewalls in the form of Pyromet Maxicoolers. This maximises energy removal, and eliminates the need for annual refractory repairs.
The flotation circuit consists of two 30 m³ cascading Outokumpu tank cells, followed by 14 flotation cells, currently functioning as a single rougher bank. Concentrate is pulled from each of the two tank cells and every flotation cell, then sent to the flue dust thickener. Tailings from the flotation cells are pumped to a tailings dam.
Chrome recovery plant
The plant has two modules, each employing a multi-stage configuration of separators and spirals. It produces two final chromite concentrates, one a metallurgical grade concentrate and the other a chemical grade. The chrome content of the concentrates is approximately 42 %. The two concentrates are pumped to their respective stockpile areas via their own dewatering separators. At the stockpile facility, the chromite is loaded onto trucks (for delivery to domestic customers) or rail wagons (for delivery to international customers via Richards Bay).
The chrome-silica cyclone underflow from the two UG2 plants serves as the dedicated feed stream to the chrome recovery plant and is pumped to two agitated feed surge tanks. From the surge tanks the slurry is delivered to desliming/separator cyclones located prior to the spirals circuit. The cyclone underflow then reports to the spirals circuit by gravity feeding. The spiral nests have been arranged to ensure optimum and equal feed distribution between all individual spirals starts. Where possible, the various stages of rougher, cleaner and recleaner spirals are stacked vertically above one another to maximise gravity feed arrangements to each section.
Summary:
Process Water
The required water will be sourced from the chrome recovery plant process water storage tank. There will not be a need for top-up water during normal operation.
Potable Water
Amandelbult Mine Complex sources most of its potable water from Magalies Water via the Vaalkop Reservoir A 3.5 Ml/d reverse osmosis treatment plant at Dishaba shaft treats water removed from underground to potable standards for domestic purposes at the shaft areas, and a number of other destinations.
Pipeline
As part of the Dishaba East Project there is various surface infrastructure which support the underground mining.
Surface mine water storage dams:
The existing 2 ericson dams will be refurbished to supply water via two separate 250mm diameter pipeline to the adit, before going underground. The length of the pipeline will not exceed 150m, prior to going vertically down the shaft to the relevant station.
Water from underground will be treated and pumped to surface to these ericson dams. Any overflow from these dams will be pumped to the 49E turf overflow dams as is currently practiced, for re-use at Dishaba Mine.
Active Dewatering storage dams: Clear fissure water at source will be pumped from underground to surface into 2 new 4,0m diameter Ericson dams. This water will be used where cleaner water is required, e.g., at the concentrator.
Potable water supply: A 100mm diameter pipeline with a length of 800m, will be installed from the nearby shaft area to the project area.
Tumela 15E Extension Project associated surface infrastructure
Water Handling
Clear water supply to underground
Two ericson dams will be installed on surface to supply water to the underground operations through a 250mm diameter pipeline. The pipeline above ground will not exceed 150m in length, prior to going down the shaft to gravity feed the water
Underground water storage dams
Water from underground will be pumped to surface, and discharge into the two off settler water dams. Any overflow from these dams will be pumped to the TSF overflow dam via two 200mm pipelines with a length of 1500m.
Potable water supply
In order to provide the project site with potable water, a 100mm diameter pipeline will be constructed. This pipeline will tie in to the existing pipeline located at the nearby living quarters and will have a length of 800m.
Tumela 1 Sub Shaft supporting surface infrastructure
Water Handling
The Tumela 1 Sub Shaft will use the existing two ericson dams. A new pipe will be required to feed the mine service water, via gravity, from the ericson dam to the Million Dollar Dam. The pipeline will have a diameter of 200m and a length of 245m.
The existing Million Dollar Dam will be rehabilitated and re-lined for use as storage of excess mine service water from the Ericson dams. A new water pump station will need to be developed as well as a new pipeline from the Million Dollar Dam to the Zero Dam. The Pipeline will have a diameter of 300mm and a length of 7 km.
Potable water will be piped to all downcast ventilation shafts, diesel, emulsion and shotcrete/concrete plant sites within Tumela 1 Sub Shaft. This pipeline will tie into the existing line which services the existing refrigeration plant and will routed along the existing services corridor up. It is anticipated that the pipeline will have a diameter of 250mm and a length of 1500m.
Services at the general buildings
In order to accommodate the Tumela 1 Sub Shaft general buildings a new wastewater drainage pipe will be required. It will route along the existing gravel access road from the 28W RB terrace down and will tie into the existing wastewater pipeline at Tumela 1 Shaft. The pipeline will have a diameter of 200mm and a length of 390m.
Raisebore Shaft (15 Level) and associated surface infrastructure. Water services all pipelines will be approximately 2.2 km.
Commodity Production
Commodity | Product | Units | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 |
PGM
|
Metal in concentrate
|
koz
| 580 | 634 | 712 | 773 | 608 | 893 | 868 | 858 | 885 | 838 |
Platinum
|
Metal in concentrate
|
koz
| 294 | 322 | 361 | 392 | 307 | 454 | 443 | 438 | 459 | 430 |
Palladium
|
Metal in concentrate
|
koz
| 136 | 148 | 165 | 180 | 143 | 209 | 205 | 202 | 207 | 199 |
Rhodium
|
Metal in concentrate
|
koz
| 53 | 58 | 65 | 70 | 56 | 81 | 77 | 75 | 75 | 71 |
Iridium
|
Metal in concentrate
|
koz
| 19 | 21 | 24 | 26 | 20 | 29 | 28 | 27 | 27 | 25 |
Ruthenium
|
Metal in concentrate
|
koz
| 75 | 82 | 94 | 102 | 79 | 116 | 111 | 110 | 110 | 106 |
Gold
|
Metal in concentrate
|
koz
| 2.3 | 2.7 | 3.1 | 3.5 | 3 | 4.8 | 5.2 | 5.5 | 6.6 | 6.9 |
Nickel
|
Metal in concentrate
|
kt
| 0.7 | 0.7 | 0.9 | 1 | 0.8 | 1.2 | 1.3 | 1.4 | 1.6 | 1.7 |
Copper
|
Metal in concentrate
|
M lbs
| 0.6 | 0.6 | 0.7 | 0.8 | 0.7 | 1.1 | 1.2 | 1.4 | 1.8 | 2 |
Chrome
|
Concentrate
|
kt
| 846 | 918 | 772 | 884 | 786 | 909 | 832 | 654 | 235 | |
Operational metrics
Metrics | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 |
Ore tonnes mined
| 4.4 Mt | 5.8 Mt | 5 Mt | 5.8 Mt | 4.7 Mt | 6.12 Mt | 6.32 Mt | 7,049 kt | 6,501 kt | 6,501 kt |
Tonnes milled
| 4,070 kt | 4,385 kt | 5,268 kt | 5,925 kt | 4,516 kt | 7,057 kt | 6,961 kt | 7,049 kt | 7,058 kt | 6,501 kt |
Production Costs
| Commodity | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 |
Cash costs
|
PGM
|
1,217 / oz USD
|
1,189 / oz USD
|
1,127 / oz USD
|
1,127 / oz USD
|
1,031 / oz USD
|
873 / oz USD
|
864 / oz USD
|
815 / oz USD
|
Cash costs
|
Platinum
|
|
|
|
|
|
1,719 / oz USD
|
1,695 / oz USD
|
1,596 / oz USD
|
Total cash costs
|
Platinum
|
|
|
|
|
|
1,725 / oz USD
|
1,717 / oz USD
|
|
All-in sustaining costs (sold)
|
3E (Pt, Pd, Au)
|
1,070 / oz ** USD
|
1,275 / oz ** USD
|
1,381 / oz ** USD
|
1,356 / oz ** USD
|
1,426 / oz ** USD
|
985 / oz ** USD
|
|
|
All-in sustaining costs (sold)
|
PGM
|
|
|
1,344 / oz ** USD
|
1,213 / oz ** USD
|
1,499 / oz ** USD
|
|
|
|
All-in sustaining costs (sold)
|
Platinum
|
|
|
|
|
|
390 / oz ** USD
|
794 / oz ** USD
|
955 / oz ** USD
|
** Net of By-Product.
Operating Costs
| Currency | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 |
Total operating costs ($/t milled)
|
ZAR
| 2,931 | 2,929 | 2,278 | 1,986 | 2,109 | 1,510 | 1,300 | 1,197 | 1,092 |
Mine Financials
| Units | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 |
Sustaining costs
|
M ZAR
| 1,180 | 1,478 | 1,191 | 1,063 | 741 |
998
|
811
|
563
|
Capital expenditures
|
M ZAR
| 1,322 | 1,792 | 1,736 | 1,555 | 1,184 |
1,172
|
980
|
456
|
Revenue
|
M ZAR
| 20,340 | 23,866 | 32,889 | 41,662 | 18,248 |
17,424
|
13,192
|
11,423
|
EBIT
|
M ZAR
| 2,505 | 5,094 | 16,070 | 23,237 | 7,060 |
4,311
|
1,269
|
450
|
EBITDA
|
M ZAR
| 3,630 | 5,962 | 16,962 | 24,151 | 7,809 |
5,132
|
2,031
|
1,173
|
Operating Cash Flow
|
M ZAR
| | | 16,134 | 24,766 | |
|
|
|
Personnel
Job Title | Name | Profile | Ref. Date |
General Manager
|
Charl Engelbrecht
|
|
Mar 24, 2025
|
Production Manager
|
Solly Khumalo
|
|
Mar 24, 2025
|
Safety Manager
|
Alwyn Smit
|
|
Mar 24, 2025
|
Sr. Engineering Manager
|
Willem van Loggerenberg
|
|
Mar 24, 2025
|
Sr. Ventilation Engineer
|
Mothusi Buthelezi
|
|
Mar 24, 2025
|
Employees | Contractors | Total Workforce | Year |
11,411
|
1,013
|
12,424
|
2024
|
12,342
|
905
|
13,247
|
2023
|
12,326
|
1,093
|
13,419
|
2022
|
13,559
|
924
|
14,483
|
2021
|
13,980
|
1,627
|
15,607
|
2020
|
14,232
|
1,431
|
15,663
|
2019
|
14,490
|
1,300
|
15,790
|
2018
|
14,108
|
1,714
|
15,822
|
2017
|
13,879
|
1,147
|
15,026
|
2016
|