Mining Intelligence and News
Sweden

Aitik Mine

Click for more information

Categories

Overview

Mine TypeOpen Pit
StatusActive
Commodities
  • Copper
  • Gold
  • Silver
Mining Method
  • Truck & Shovel / Loader
Production Start1968
Mine Life2048
SnapshotAitik is the world’s most productive open-pit copper mine. Aitik is mined as an open pit complex consisting of the main pit, “Aitik”, and two satellite pits “Salmijärvi”, which was mined out during 2023, and “Liikavaara”, which will begin production in 2024.

A pilot for Autonomous Hauling System – the first of its kind in Europe – was conducted in Aitik with seven trucks. The Autonomous Haulage System is planned for integration in regular operations in 2025.

Execution of Aitik’s SEK 5 billion dam safety project started in April 2023 and will run for two years.

In 2023, milled volumes in Aitik were below the record levels from 2022. Several production issues contributed negatively. An unplanned maintenance stop and unusually unfavorable weather conditions lowered Aitik’s fourth quarter milled production by 2 Mt.

Owners

SourceSource
CompanyInterestOwnership
Boliden AB 100 % Indirect
Boliden Mineral AB (operator) 100 % Direct
Boliden Mineral AB owns 100 % of the Aitik mine.

Deposit type

  • Porphyry
  • IOCG
  • Hydrothermal

Summary:

The Aitik, Salmijärvi, and Aitik East deposits occur along a largely continuous elongate mineralized trend (the Aitik-Salmijärvi mineralization) stretching approximately 5 km along strike from north to south averaging about 500 m in width.

Host rocks of the mineralization at the Aitik deposit consist mainly of paleo-proterozoic (ca. 1.89 billion years) muscovite schists, biotite gneisses, and amphibole-biotite gneisses of volcanic and volcanoclastic origin, crosscut locally by diorite intrusive units. In places the diorite intrusive make up a significant proportion of the mineralized volume, but typically at lower than average grade. Foliation is well developed in the host rocks, dipping at about 50 degrees to the west. The mineralization is mainly structurally controlled and the main mineralisation; Aitik is delineated by a hangingwall thrust and a footwall shear. Main sulfide minerals in the deposit are chalcopyrite, pyrite and pyrrhotite, with significant accessory minerals including magnetite, molybdenite and sulfates. The entire package has been metamorphosed to amphibolite grade resulting in significant recrystallization and coarsening of both sulfide and silicate minerals. Late granite pegmatite dikes crosscut the mineralized host rocks and are generally weakly mineralized to barren.

Mineralization at the Salmijärvi and Aitik East deposits is very similar in nature to the Aitik deposit, with the exception that host rocks are strongly dominated by amphibole-biotite gneisses and local diorite. Sulphide mineralization in these deposits is dominated by chalcopyrite, pyrite and pyrrhotite, although at typically lower grade than in the Aitik deposit.

About 3 km to the east, on separate and volumetrically smaller mineralized trend, sits the paleoproterozoic Liikavaara Cu-(W-Au) deposit. At Liikavaara the mineralisation is hosted by quartz±tourmaline-calcite veins, calcite veins and aplite dykes that cross-cut biotite-amphibole schists and gneisses, steeply dipping to the west. The mineralisation is mainly chalcopyrite, pyrrhotite and pyrite, accessory minerals are sphalerite, galena, scheelite, molybdenite and magnetite. Liikavaara shows slight enrichments in Au, Ag and Bi.

Reserves at December 31, 2023

The cut-off for the Mineral Reserve is based on location cost analysis and varies between 0.04% and 0.14% Cu.

The cut-off for the Mineral Resource is 0.06%.
CategoryTonnage CommodityGrade
Proven & Probable 1,143,000 kt Copper 0.23 %
Proven & Probable 1,143,000 kt Gold 0.16 g/t
Proven & Probable 1,143,000 kt Silver 1.3 g/t
Measured & Indicated 589,000 kt Copper 0.17 %
Measured & Indicated 589,000 kt Gold 0.12 g/t
Measured & Indicated 589,000 kt Silver 0.8 g/t
Inferred 351,000 kt Copper 0.17 %
Inferred 351,000 kt Gold 0.07 g/t
Inferred 351,000 kt Silver 0.7 g/t

Mining Methods

  • Truck & Shovel / Loader

Summary:

Aitik is a Palaeoproterozoic porphyry Cu-Au-Ag deposit, mined as an open pit complex consisting of the main pit, “Aitik”, and two satellite pits “Salmijärvi”, which was mined out during 2023, and “Liikavaara”, which will begin production in 2024. The mining in Aitik took place at three pushbacks of the main Aitik pit - designated S3, N6 and N7.

The ore is mined in two open pits along the same mineral deposit. The main pit is called Aitik and measures 4 km by 1.1 km at the surface, with the deepest point currently at 555 meters from the surface. In 2010, mining commenced in a second pit called Salmijärvi which has reached a depth of 305 meters below the surface, with a surface footprint of 0.9 by 0.6 km. The pit is being depleted during 2023 and no further expansions are planned for this area. The main pit will be expanded in all directions with five new pushbacks. Mining of pushback S3 in the southern part of the main pit started in 2016. Prestripping of pushback N7 commenced in 2019 to allow mining to start during 2020.

The ore and waste rock are blasted in 15-meter-high benches and are loaded on 300 tons capacity-size trucks by large rope shovels or hydraulic excavators. Ore from the deeper parts of the main pit is fed to an in-pit-crusher, while ore from pushbacks near the surface is transported to a surface crusher situated on the south-east side of the main pit. Waste rock is separated in the loading process and hauled by trucks to dumps at the surface where potentially acid-forming waste is dumped separately from non-acid-forming waste.

Holes for blasting are drilled with electric drills from Bucyrus and Atlas Copco. Hole depth: 16-17 m Hole diameter: 311 mm Drill attern: 7x9 m Between 200-300 holes are drilled for each round of blasting. A normal blast round produces around 700 000 tonnes of rock for extraction.

Boosters are loaded into the holes followed by emulsion explosives. Explosives: Emulsion explosives (Kemitti-610) from Forcit, about 1 tonne of explosive is used in each hole.

With the help of shovels from Bucyrus, P&H, Komatsu and wheelloaders from Caterpillar, the blasted rock is loaded on to trucks for further tranportation. The largest trucks, CAT 795F, holds about 313 tonnes. A bucket can hold 45 m³ rock (Komatsu 26 m³). The ore is transported to the crusher and the waste rock to a waste rock dumpsite. The machines are equipped with the positioning system Minestar.

In Aitik, ore haulage has been automated to a high degree, which enables for largescale production while also ensuring a safe workplace with good climate performance. In 2023 the open pit’s reserves and planned production will provide a further 27 years of mining.

The start-up of production at Aitik’s Liikavaara deposit drew closer with the relocation of the E10 public road and the building of a road between the new open pit and the crusher.

Comminution

Crushers and Mills

TypeModelSizePowerQuantity
Gyratory crusher FLSmidth Fuller-Traylor 60" x 113" 2
Gyratory crusher Metso Superior™ 60-110E 2
Cone crusher 2
AG mill Metso 11.6m x 13.7m 22.5 MW 2
AG mill 2
Pebble mill Metso 8.1m x 11.3m 10 MW 2

Summary:

Aitik currently operates in-pit and near-surface crushers to facilitate ore transport. As part of the Aitik 36 expansion project, two gyratory crushing stations with a combined capacity of 8000 t/h were installed inside the pit to allow for the crushing of ore mined from deep parts. To further increase production, the Aitik 45 expansion project included the construction of an additional crushing plant consisting of two gyratory crushers located between the two open pits on the surface, each with an approximate capacity of 9000 t/h.

Ore handled by the crushers in pit is transported on conveyor belts to an intermediate storage on surface, where it is mixed with ore from the surface crusher fed in by a separate conveyor line. From the intermediate storage another conveyor belt transports the ore up to the main ore storage beside the processing plant. The main ore storage has a storage capacity corresponding to about one day’s production, providing buffer for the production.

In the processing plant the ore is ground in two stages, with autogenous grinding in the primary stage and pebble mill grinding in the second. The milled ore is classified using a spiral classifier.

Two grinding lines are present in the mine, both of which are fully autogenous. The grinding lines are operated in a closed circuit consisting of a primary AG mill, a secondary pebble mill and a screw classifier. The AG primary mills are the largest in the world, having a power rating of 22.5 MW, diameter of 11.6 m, length of 13.7 m and volume of 1400 cm3 (June 2011). Grinding capacity ranges from 2,500-3,200 ton/hr while operating work index ranges from 9.7 to 12.4 kWh/ton. These values are highly dependent on the hardness of the ore. The grinding line targets a P80 size of 175 µm for the downstream process. This particle size is based on the liberation analysis of sulphides, mainly chalcopyrite, in the ore.

Also, each primary AG mill operates in a closed circuit with a cone crusher to crush salient pebbles aiming at increasing the AG mill’s throughput .

Regrinding circuit is consist of autogenous mills that operate in a closed-circuit configuration with hydro cyclones.

Processing

  • Crush & Screen plant
  • Flotation
  • Dewatering
  • Filter press

Summary:

The milled ore is sent for concentration through a series of froth flotation stages, namely, rougher, scavenger and four cleaning stages.

Milled ore is classified using a spiral classifier. Mineral separation is done by flotation and a copper concentrate is produced. The tailings are separated into a high-sulphur (cleaner tail) and a low-sulphur (rougher tail) fraction, deposited separately at the tailings management facility. The copper concentrate is dewatered using thickeners and air pressure filters. The precious metals also report to the copper concentrate. The copper concentrate is trucked to an on-site railway terminal and reloaded for further transport by rail to the Boliden Rönnskär smelter in Skelleftehamn.

The plant produces a final concentrate containing 20-23% copper with gold, silver and molybdenum. Copper recovery is at 85-95% while silver and gold is at 65% and 50%, respectively. Molybdenum is currently not being recovered.

Recoveries & Grades:

CommodityParameter202320222021202020192018201720162015
Copper Recovery Rate, % 90.290.5
Copper Head Grade, % 0.180.20.220.240.250.290.280.220.21
Copper Concentrate Grade, % 24.625.225.524.824.224.624.822.121.9
Gold Recovery Rate, % 53.558.6
Gold Head Grade, g/t 0.080.10.110.130.130.140.130.110.11
Silver Recovery Rate, % 76.475.3
Silver Head Grade, g/t 0.80.860.871.061.171.821.982.112.45

Production

CommodityProductUnits202320222021202020192018201720162015
Copper Metal in concentrate M lbs 141174176201201219216157148
Copper Concentrate kt 261314314368377404394320307
Gold Metal in concentrate oz 55,41278,14383,947100,56398,470101,28593,19768,12765,666
Silver Metal in concentrate koz 8049008481,1131,2211,7651,9891,8201,976

Operational metrics

Metrics202320222021202020192018201720162015
Annual processing capacity 45 Mt45 Mt
Ore tonnes mined 40,689 kt43.3 Mt40,100 kt41,661 kt
Waste 35,301,710 t30,472,000 t31,438,000 t
Total tonnes mined 75,991,144 t73,768,675 t71,602,000 t
Tonnes milled 40,689 kt43,297 kt40,100 kt41,661 kt40,661 kt38,472 kt39,045 kt36,051 kt36,361 kt

Production Costs

CommodityUnits2023202220212020201920182017
C1 cash costs Copper USD 1.91 / lb **   1.28 / lb **   1.08 / lb **   0.65 / lb **   0.76 / lb **   0.77 / lb **   0.82 / lb **  
** Net of By-Product.

Financials

Units2023202220212020201920182017
Capital expenditures M SEK 5,403  3,131  1,653  1,823   1,985   1,576   1,534  
Revenue M SEK 6,338  7,365  7,211  6,295   5,818   6,017   5,487  
Operating Income M SEK 1,419  3,076  3,281  2,296   2,149   2,494   2,073  

Heavy Mobile Equipment

HME TypeModelSizeQuantityStatusRef. DateSource
Excavator Komatsu PC 7000 1 Existing Jan 25, 2022
Excavator Komatsu PC 7000 1 Required Jan 25, 2022
Loader Caterpillar 994F 18 m3 Existing Dec 31, 2012
Loader LeTourneau L2350 38 m3 1 Existing Jan 25, 2022
Shovel (rope) Komatsu 4100 XPC 45 m3 Existing Jan 25, 2022
Truck (haul) Caterpillar 795F AC 313 t 14 Existing May 10, 2022
Truck (haul) - AV Komatsu 930E-5 290 t 11 Existing Oct 25, 2021
Truck (haul) - AV Komatsu 930E 1 Existing Sep 25, 2024

AV - Autonomous

Personnel

Mine Management

Job TitleNamePhoneEmailProfileRef. Date
Environmental Manager Åsa Sjöblom 0970-729162 asa.sjoblom@boliden.com Jun 12, 2023
General Manager Thomas Sundqvist 0970-729011 thomas.sundqvist@boliden.com LinkedIn Jun 8, 2024
Mill Manager Andreas Berggren LinkedIn Jun 13, 2024
Mine Technical Services Manager Patrik Gillerstedt LinkedIn Jun 13, 2024
Project Manager Johanna Lundin LinkedIn Jun 8, 2024
Technical Services Superintendent Åsa Bergstrand LinkedIn Jun 8, 2024

EmployeesYear
814 2023
932 2022
770 2021
800 2020
750 2019
700 2018
650 2017

Aerial view: