Solomon Hub Operation (Firetail Mine, Kings Valley Mine) (FMG Operation)

This page is not tailored to
devices with screen width under 750 px.
 Location:
48 km NW from Wittenom, Western Australia, Australia

  Regional Office:
Level 2, 87 Adelaide Terrace
East Perth
Western Australia, Australia
6004
Phone  ...  Subscription required
Fax+61-8-6218-8880
WebsiteWeb
Additional Resources for Suppliers & Investors
Drill results over 30 g/t Au
Stay on top of recent discoveries.
Search drill results by commodity and grade.
Largest mines in the Americas
Mining and mill throughput capaciites.
Full profiles of select mines and projects.
Deepest underground mines
Shaft depth and mill throughput data.
Full profiles of select mines and projects.
Heavy mobile equipment
HME type, model, size and quantity.
Full profiles of select mines and projects.
Permitting and construction projects
Projects at the permitting or construction stage. Full profiles of select projects.
Mines with remote camps
Camp size, mine location and contacts.
Full profiles of select mines and projects.
Mines & projects in Australia
A list of country's mines and projects.
Full profiles of select mines and projects.
  • Overview
  • Owners
  • Geology
  • Mining
  • Processing
  • Production
  • Reserves
  • Fleet
  • Personnel
  • Filings & News

Thank you for browsing through mine profiles compiled by the Mining Data Online team.

Would you like to subcribe or schedule a Demo?
  • Name:
     
  • Company:
     
  • Position:
     
  • Phone:
  • Email:
  • Message:

Overview

StageProduction
Mine TypeOpen Pit
Commodities
  • Iron Ore
Mining Method
  • Truck & Shovel / Loader
  • Backfill
Processing
  • Wet Screening
  • Gravity separation
  • Dry Screening
  • Desand plant
Mine Life20 years (as of Jan 1, 2019)
Latest NewsFortescue guides project development with contract awards     January 22, 2021


Owners

Source: p. 108
CompanyInterestOwnershipInvestor's Info
Fortescue Metals Group Ltd. 100 % Indirect

Deposit Type

  • Bedded Iron (BID)
  • Channel Iron (CID)
  • Detrital Iron (DID)


Summary:

The Solomon Project area (Firetail, Kings & Queens deposits) is situated approximately 60 kilometres to the north of the Tom Price township in the northern Hamersley ranges. Outcropping geology in the project area is dominated by the Dales Gorge, Whaleback Shale and Joffre Members of the Brockman Iron Formation which hosts large BID throughout the Hamersley Province. The Firetail deposit contains the major tonnages of BID at Solomon, where geological favourable environments have allowed for the formation and preservation of large tonnages of iron mineralisation.

Incised into this bedrock geology are regional palaeochannel systems, predominantly one to two kilometres in width, and stretching for tens of kilometres. During the Miocene period deep chemical weathering and erosion of the generally iron rich material into these fluvial channels formed CID. Through Fortescue’s interpretation of drill hole results, the CID can be subdivided into an upper ‘hard CID’ and a lower ‘ochreous CID’. Clay lenses are observed as semi-discrete bands often several meters thick, sometimes of a poddy nature although often traceable between drill holes. Approximately 40 km of buried CID is preserved in the Kings CID system, with a further 25 km of CID located in the Serenity deposit to the west. Other CID occurrences are also known throughout the Solomon project area. The material overlying the CID (and other areas) has been eroded from adjacent mineralised and un-mineralised bedrock. This clastic material is concentrated into horizons of elevated iron grade termed DID, which forms part of the sequence of overlying late Tertiary aged alluvial and colluvial deposits.


Mining Methods

  • Truck & Shovel / Loader
  • Backfill


Summary:

The Solomon Mining Hub is an operational mine. The Solomon Mine is composed of many parts including; mining of open pits, processing of the ore and the handling of mined waste rock, the handling and storage of process waste (tailings), transport of product, water management and other infrastructure.

Firetail
The Firetail deposit consists of two mining areas, being the north and south limbs of a regional anticline (Firetail North and Firetail South). Each mine area extends over a length of approximately 7 km and is on average approximately 700 m in width.

The total proposed disturbance footprint associated with the Firetail mine and associated infrastructure is approximately 1,000 ha. All mining occurs above the water table and therefore no site specific groundwater management measures is required.

Kings
The Kings deposit is comprised of four main mine areas - Zion, Valley of the Kings, Trinity and Valley of the Queens. The deposit is located within a broad valley system extending approximately 35 km in length, with a width of 0.5 km to 2 km. The Kings deposit consists of CID with some BID and DID.

Multiple pits within the Kings mine is operated concurrently, with each pit approximately 100 ha in area. The total proposed mining disturbance and infrastructure footprint a ssociated with the Kings mine i s approximately 3,000 ha.

The Kings CID deposit is located below the water table and will require controlled dewatering throughout the life of the mine to achieve and maintain safe, dry mining. Water recovered during dewatering that is excess to mine processing and other uses, will be disposed of via reinjection into the CID aquifer.

Mining Methods
All stages of the mining operations is undertaken by contract mining, under the supervision of Fortescue site mining personnel. Mining uses conventional open pit methods of drill and blast followed by load and haul.

Excavators is employed to dig the material from working mine faces. The excavators load material into haul trucks for transport to either waste dump or ore stockpile locations.

Waste will be transported by haul trucks to waste dumps, located adjacent to the mine pits in the early years, and into mined-out areas of the pits in later years.

Mining is occured at multiple spatially separate pits, each working multiple mining faces simultaneously. The Run of Mine (ROM) ore from each mining area is blended at a number of separate crushing hubs to ensure a consistent mix of ore to achieve the required blend and contaminant levels. Two ROM pads and associated ROM feed bins are proposed at each crushing hub, one each for the CID and the BID/DID products, both of which feed conveyors that is transported ore to the OPFs. In some cases, stockpiles of ROM ore is employed to further enhance the degrees of blending.

Pit Backfilling and Waste Disposal
Overburden from initial mining areas will be transported by haul trucks to permanent external waste dumps until sufficient voids are available for backfilling. In later years of mining, waste will be backfilled into depleted mine voids. Fortescue estimates that approximately 270 Mt of waste will be required to be disposed of to external waste dumps, while 1,730 Mt will be backfilled into mine voids.

The following strategy is envisaged for waste disposal:
- Firetail: During the initial phase of mining, most waste will be disposed of in an external waste dump located in the valley between the Firetail North and South deposits. After about Year 7, opportunities will exist to backfill mined out areas of the Firetail pits. The external waste dump will hold approximately 70 Mt o f waste and the remaining 40 Mt of Firetail waste will be back-filled in-pit.

- Kings mine (eastern end): Initial waste will be stored at the head of a valley at the eastern part of the deposit. This waste dump is likely to store approximately 100 Mt of waste. Some waste will also be used to construct the tailings embankments for a TSF. On completion of the initial mining stage, waste will be back-filled into previously mined areas to levels resembling the pre-mining topography. The estimated volume of waste to be disposed in-pit is approximately 850 Mt.

- Kings mine (western end): Waste from the eastern end of Valley of the Queens will be stored in-pit as a continuation of the Valley of the Kings mining. Mining within the western end of Valley of the Queens will initially require an external dump for storage of approximately 100 Mt of waste. Once sufficient void space is available, in- pit backfilling will commence and waste will be back-filled into previously mined areas to levels resembling the pre-mining topography. The estimated volume of waste to be backfilled into in-pit dumps is approximately 840 Mt.

Although pits will be backfilled, the original landform of the area cannot be fully reinstated as the volume of material removed through mining will be significant. Fortescue’s proposed mining method of pit backfilling is expected to significantly reduce the risk of mine closure impacts by creating the final mine void for backfilling early in the life of the Solomon Hub Operation.


Crushing and Grinding


Processing

  • Wet Screening
  • Gravity separation
  • Dry Screening
  • Desand plant

Source: Subscription required

Summary:

Ore Processing
The Run of Mine (ROM) ore from each mining area is blended at a number of separate stockpiling areas and crushing huba to ensure a consistent mix of ore to achieve the required blend.

Crushing will involve combinations of primary, secondary and tertiary crushing as well as gravity concentration of the combined with the separation of sand and clay waste material. ROM pads and associated ROM feed bins are proposed at each crushing hub. Ore currently carried from the crushing hubs via conveyors to the OPFs at Kings and Firetail.

The mined ROM ore is transported to elevated pads (ROM pads) for tipping into a ROM feed bin at a number of separate primary crushing hubs. Two primary crushing hubs, with one for the Firetail (for Brockman ore) and one for the Kings (with the one for the Kings project comprising two crushing streams for CID and DID ore, and for the Firetail project comprising a single stream for BID ore). The primary crusher system consis ........


Combined production numbers are reported under FMG Operation

Operational Metrics:

Metrics202020192018201720162015
Annual production capacity  ......  Subscription required  ......  Subscription required  ......  Subscription required  ......  Subscription required70 Mt of iron ore70 Mt of iron ore
Subscription required - Subscription is required.

Reserves at June 30, 2020:
Solomon Hub and Eliwana Mineral Resources are quoted above a cut-off grade of 51.5% Fe.

CategoryTonnage CommodityGrade
Proven 101 Mt Iron (hematite) 57.3 %
Probable 533 Mt Iron (hematite) 57.7 %
Proven & Probable 634 Mt Iron (hematite) 57.6 %
Measured 208 Mt Iron (hematite) 55.3 %
Indicated 1,277 Mt Iron (hematite) 55.3 %
Inferred 636 Mt Iron (hematite) 54.9 %
Total Resource 2,121 Mt Iron (hematite) 55.2 %


Heavy Mobile Equipment as of October 29, 2018:
HME TypeQuantity
Truck (haul) 70

Mine Management:

Job TitleNameProfileRef. Date
....................... Subscription required ....................... Subscription required Subscription required Aug 28, 2020
....................... Subscription required ....................... Subscription required Subscription required Aug 28, 2020
....................... Subscription required ....................... Subscription required Subscription required Aug 28, 2020
....................... Subscription required ....................... Subscription required Subscription required Aug 28, 2020
....................... Subscription required ....................... Subscription required Subscription required Aug 28, 2020
....................... Subscription required ....................... Subscription required Subscription required Aug 28, 2020
Subscription required - Subscription is required.


Corporate Filings & Presentations:

DocumentYear
................................... Subscription required 2020
................................... Subscription required 2020
................................... Subscription required 2019
................................... Subscription required 2019
................................... Subscription required 2018
Annual Report 2017
Annual Report 2016
Annual Report 2015
Annual Report 2015
Environmental Assessment 2015
Other 2011
Environmental Assessment 2010
Subscription required - Subscription is required.

News:

NewsDate
Fortescue guides project development with contract awards January 22, 2021
Fortescue contracts Central Systems for Solomon Hub October 1, 2020
Fortescue gains approval for Queens Valley development May 22, 2019