The operation scenario studied for the FS involves:
• Open Pit mining at an average mining rate of 12.8 Mt per year.
• Gold process facility with a 1.46 Mtpa (4,000 t/d) capacity.
• Approximate 6-month ramp up period in Year 1 (YR1) for process facility.
• 1-year pre-production mining period to coincide with Tailings Management Facility Initial Stage development.
The FS is based on a conventional truck-shovel open pit mining operation within two pits. The open pit production period is approximately 10.9 years with 1 year of pre-production (prior to process plant start-up).
Waste Rock Disposal Design
Waste rock generated from the open pit will require the development of waste rock storage areas. The waste generated from the open pit includes waste rock, till, historical tailings, and topsoil and organics.
The proposed mine plan will generate approximately 126.8 million tonnes of waste material, which includes overburden. Assuming a swell factor of 30%, a volume of 61.7 million m3 of waste storage is required.
Open Pit Mining Operation
A mining contractor would be responsible, with the guidance of the Company technical staff, to provide suitable equipment and operational procedures to meet the target production. The mining equipment will depend on the available equipment of the selected mining contractor.
Drilling is expected to be performed on eight-metre benches. For ore-control may be excava ........