The mining operations are planned to use conventional open pit mining methods and equipment. The proposed Pebble mine would be a conventional drill, blast, truck, and shovel operation with an average mining rate of approximately 70 million tons per year and an overall strip ratio of 0.12 ton of waste per ton of mineralized material.
The open pit would be developed in stages, with each stage expanding the area and deepening the previous stage. The final dimensions of the open pit would be approximately 6,800 ft long and 5,600 ft wide, with depths to 1,950 ft.
The projected mining schedule was generated using five pushbacks and was based on a maximum processing capacity of 180,000 ton/d. Based on the selected ultimate pit, final pit design and the generated production schedule, the Project’s total LOM is 21 years, including 1 year of pre-stripping followed by 20 years of production. Over the 21-year LOM, the pit would produce 1,291 million tons of mineralized material and 153 million tons of overburden and waste rock. The LOM stripping ratio (defined as waste material mined, in tons, divided by mineralized material mined, in tons) is 0.12:1. Approximately 1.4 billion tons of material are planned to be mined during the production phase.
The Project production fleet would use the most efficient mining equipment available to minimize fuel consumption per ton of rock moved. Most mining equipment would be diesel-powered. This production fleet would ........
