The Project comprises two main deposits – Razafy and Razafy Northwest (NW), broadly 1.5km apart, spread out over approximately 2km2. An initial 0.5Mtpa process plant will be located about 0.5km north of Razafy, to be expanded to 1.0Mtpa in Year 3, ready for milling 1.0Mtpa from Year 4 onwards – staged development.
It is envisaged that two waste dumps will be constructed at Razafy, a smaller one to the east and a larger one to the west of the pit. A single waste dumps will be constructed at Razafy NW.
Mining will be carried out using conventional open pit methods of drill and blast followed by load and haul.
The total material movement at the Project has been estimated at approximately 2Mtpa for the first three years of operation, increasing to a maximum of 4Mtpa in subsequent years.
It is believed that a mining fleet comprising 60t to 80t excavators and 30t to 40t capacity trucks would be suited for the scale of mining envisaged.
The mining operation would excavate and load the ore and waste in accordance with the marked ore and waste boundaries and ensure minimum dilution and maximum recovery of ore.
The ore is to be hauled to a single ROM pad located to the north of Razafy and east southeast of Razafy NW.
The bulk of the waste will be dumped in areas adjacent to the pits, with 26% required for constructing the TSF embankment and 3% for other mining related infrastructure such as the Run of Mine (“ ........