Mining Intelligence and News
Australia

Bootu Creek Mine

Click for more information

Categories

Overview

Mine TypeOpen Pit
StatusCare and Maintenance
Commodities
  • Manganese
Mining Method
  • Truck & Shovel / Loader
Production Start... Lock
SnapshotProduction at the Bootu Creek Manganese mine ceased as planned during the quarter ended 31 December 2021. The Mine was placed under care and maintenance mode since the end of January 2022.

The primary focus was to make ready, survey, and cross-rip designated areas of the Mine in preparation for aerial seeding for reforestation and this was completed in mid-November 2022. Rehabilitation of the remaining areas will continue in 2023.

Owners

SourceSource
CompanyInterestOwnership
OM Holdings Ltd. 100 % Indirect
OM (Manganese) Ltd. (operator) 100 % Direct
OM (Manganese) Ltd (“OMM”) is a wholly owned subsidiary of the OM Holdings Ltd and one of the Group’s core businesses with its main activities being exploration and mining of manganese ore at the Bootu Creek Mine.

Deposit type

  • Stratabound

Summary:

The Bootu Creek manganese deposits are strata-bound, located at the contact between the underlying dolomite-siltstone Attack Creek Formation and the overlying ridge forming sandstone of the Bootu Formation in the Tomkinson Group, within the Ashburton Province of the Palaeozoic Tennant Creek Inlier. The mineralised manganese bearing sandstone horizon is folded around the gentle NNW plunging Bootu Syncline, can be traced for 24 km and dips around 30o towards the fold axis.

The manganese ore is supergene enriched within a deeply weathered profile. The Bootu Creek manganese resource models have a combined strike length of 16 km, with deposit models ranging from 0.7 km to 2.9 km in length. Mineralisation widths vary from 3 m to 15 m and ore mineralogy consists predominately of Pyrolusite and Cryptomelane in a silica rich gangue within the supergene zone, overlaying a Rhodochrosite and Braunite unweathered zone at depths of greater than 90m from surface.

Reserves

Lock

- subscription is required.

Mining Methods

Lock

- subscription is required.

Comminution

Crushers and Mills

Lock

- subscription is required.

Processing

Lock

- subscription is required.

Production

Production at the Bootu Creek Manganese mine ceased during the quarter ended 31 December 2021. Processing of the final ore occurred in January 2022.
CommodityUnits2022202120202019201820172015
Manganese kt  ....  Subscribe  ....  Subscribe  ....  Subscribe570814656761
All production numbers are expressed as concentrate.

Operational metrics

Metrics202120202019201820172015
Annual production capacity  ....  Subscribe  ....  Subscribe1,000,000 dmt of manganese concentrate1,000,000 dmt of manganese concentrate
Ore tonnes mined  ....  Subscribe  ....  Subscribe1,034,190 dmt1,819,012 dmt1,587,630 dmt1,918,137 dmt
Total tonnes mined  ....  Subscribe  ....  Subscribe5,748,339 bcm8,426,107 bcm5,970,784 bcm5,417,733 bcm

Production Costs

Commodity production costs have not been reported.

Financials

Units20182017
Revenue M AUD 229.1   136.4  

Heavy Mobile Equipment

Fleet data has not been reported.

Personnel

Mine Management

Job TitleNameProfileRef. Date
....................... Subscription required ....................... Subscription required Subscription required Oct 14, 2022

Aerial view:

Lock

- subscription is required.