Overview
Status | Care and Maintenance |
Mine Type | Underground |
Commodities |
|
Mining Method |
- Narrow reef drill & blast
|
Processing |
|
Mine Life | 2022 |
The mine produced its first concentrate for shipment in March 2009. The mine then went into care and maintenance in August 2012 and no mining or processing activities took place until it was reopened in January 2015. However, continuing adverse local and global economic and market circumstances led to the mine being placed in care and maintenance again at the end of March 2016. |
Source:
p. 13
Company | Interest | Ownership |
Phokathaba Platinum (Pty) Ltd
|
100 %
|
Direct
|
Phokathaba Platinum (Pty) Ltd (“Phokothaba”) is an incorporated Joint Venture Company established under the shareholders Agreement between Corridor and SHP (Smokey Hills Platinum (Pty) Ltd) to develop the Smokey Hills Platinum Project.
Summary:
The Smokey Hills project is located in the central portion of the eastern limb of the Bushveld complex and is underlain by rocks of the upper critical zone, which hosts two of the more important PGE-bearing units in the Rustenburg Layered Suite: the Merensky Reef and the UG2. In the Smokey Hills Project Area, the Merensky Reef is expected to occur approximately 300 m above the uG2. However, a minimum of approximately 140 m of the Merensky Reef footwall units have been removed by erosion and therefore no Merensky Reef is preserved at the Smokey Hills project. In the central portion of the eastern limb of the Bushveld complex, five chromitite layers have been identified in the Upper Critical Zone, each of which forms the base of a cyclic unit. The cyclic units are termed, from oldest to youngest the UG1, UG2, UG3 UG3A and UG3B. Each of these chromitites carries varying concentrations of PGEs. However, concentrations in the UG1 chromitite layer in all areas of the RLS have been found to be subeconomic. The UG3, UG3A and UG3B chromitite layers are generally too thin and contain insufficient concentrations of PGE mineralisation to have any reasonable expectation to support economic extraction. The UG1 chromitite layer occurs over 100 m below the UG2. The UG3 chromitite layer is approximately 0.25 m thick and occurs approximately 15 m above the UG2. The UG3A and UG3B chromitite layers are approximately 0.1 m thick, occur approximately 5 m above the UG3 and are separated by approximately 0.3 m of pyroxenite. Individual layers in the Upper Critical Zone can generally be correlated over several kilometers and as such, detailed local stratigraphic nomenclature can be established.
Dykes in this area are primarily composed of dolerite, which is generally fine-grained and of good competence, with associated areas of dense jointing and alteration. Underground dyke intersections are generally less than 10 m in width. An airborne magnetic survey has identified several swarms of northeast-striking dolerite dykes. No serious problems were encountered during mining through these features, and no significant displacements have been associated with them.
Potholes are defined as areas where normal reef characteristics are destroyed and hence, pothole areas are believed to be un-mineable and considered a geological loss. The position and size of potholes are typically unpredictable. In most instances, the potholes affect only one of the economic units. However, in minor instances, the underlying or overlying economic unit may be affected by the development of the pothole.
The Bushveld complex stratigraphy is occasionally replaced by late-stage pegmatite bodies. These pegmatite bodies have a range of compositions, from highly ultramafic to felsic.
Rolling reef and small scale undulations of the UG2 do not create geological losses but can contribute towards mining difficulties. Undulations and highly dipping (up to 50°) have been observed at Smokey Hills in the outcrop and during mining. Miners have tried to minimize difficulties associated with the mining of these areas by using up-dip methods. An area of rolling reef has been encountered during underground mining centred on the 4.4 Raise. The UG2 elevation, in relation to adit 4, was reduced by up to 40 m. This has made it difficult to mine because of the proximity of the mining lease boundary.
Mining Methods
- Narrow reef drill & blast
Summary:
When in production, the Smokey Hills mine utilises a combination of conventional narrow reef stoping methods with trackless equipment to remove blasted ore from underground workings. The mine plan has changed from an up-dip stoping method to a (mainly) breast stoping configuration. However, some up-dip mining is still planned for future operations. Stope panels and reef raises are drilled with hand-held jack hammers, and the blasted ore is removed from the working faces by means of scraper winches. The centre gully (reef raise) winch scrapes all blasted ore into a large muck bay. The ore is loaded in the muck bay with trackless equipment and transported in dump trucks to the concentrator plant. Access to the underground workings is via adits, which are developed on strike and reef.
Flow Sheet:
Summary:
The Smokey Hills Plant consists of a typical UG2 processing plant with a mill-float-mill-float (or “MF2”) configuration with a capacity of 60 ktpm.
The plant consists of the following circuits:
• jaw crushing;
• cone crushing in closed circuit with a screen;
• primary ball mill in closed circuit with a screen;
• primary flotation;
• chrome spirals recovery circuit;
• secondary ball mill in closed circuit with a cyclone;
• secondary flotation;
• PGM concentrate and tails thickening;
• PGM concentrate filtering and storage;
• reagent make-up and dosing circuits; and
• water recycling and storage.
Primary and Secondary Crushing.
The crushing circuit is of a compact design and consists of a primary crushing with secondary crushing in closed circuit with a screen.
Underground RoM material is transported via trucks and tipped onto a static grizzly. Static grizzly undersize gravitates into an ore rece ........

Recoveries & Grades:
Commodity | Parameter | 2012 |
4E (Pt, Pd, Rh, Au)
|
Recovery Rate, %
| ......  |
4E (Pt, Pd, Rh, Au)
|
Head Grade, g/t
| 3.6 |
- Subscription is required.
Production:
Commodity | Units | 2012 |
4E (Pt, Pd, Rh, Au)
|
oz
| 31,568 |
All production numbers are expressed as metal in concentrate.
Operational Metrics:
Metrics | 2015 | 2012 | 2011 |
Tonnes milled
| 308,000 t | 352,318 t | 401,773 t |
Reserves at October 1, 2016:
Category | Tonnage | Commodity | Grade | Contained Metal |
Proven
|
1,909,887 t
|
4E (Pt, Pd, Rh, Au)
|
4.54 g/t
|
279 koz
|
Probable
|
979,178 t
|
4E (Pt, Pd, Rh, Au)
|
4.59 g/t
|
145 koz
|
Proven & Probable
|
2,889,065 t
|
4E (Pt, Pd, Rh, Au)
|
4.55 g/t
|
423 koz
|
- Subscription is required.
Corporate Filings & Presentations:
- Subscription is required.
Aerial view:
- Subscription is required.