Source:
p. 6
Summary:
The Norra Kärr complex is a zoned agpaitic, peralkaline, nepheline syenite - similar in many respects to other well-known peralkaline complexes, e.g. Ilimaussaq in Greenland and Lovozero on the Kola Peninsula of Russia.
The Norra Kärr intrusive is located close (2 km) to the eastern shore of Lake Vättern, a large riftcontrolled lake. Following the Tasman exploration efforts, the Norra Kärr complex is known to be an ovoid mass with an areal extent of some 1.3 km by 450 m.
The mineralisation at Norra Kärr is at once both simple and complex. Simple in mineralogical terms in that nearly all the REE mineralisation is hosted in the complex zircono-silicate mineral eudialyte. There are minor amounts of the (probably) secondary Ca LREE-F-silicate (britholite) and trace mosandrite. The eudialyte at Norra Kärr is, relatively rich in REE compared to most other similar deposits and also contains a very high proportion of HREO.
Various studies (e.g. Sjöqvist et al, 2013 (4)), have shown that within the resource, the TREO content of the eudialyte varies between 6 and 10 %. The percentage of HREO also varies from about 30 % in the more central GTM zone to above 70 % in more distal GTC zone. The total content and distribution of the REEs within the eudialyte also varies throughout the deposit. Sjöqvist et al (4) defined three compositional varieties of eudialyte group minerals at Norra Kärr:
- Fe-rich, REE-poor, classical pink eudialyte;
- Fe-Mn-bisected, HREE-rich eudialyte from “pegmatitic” grennaite; and
- Mn-rich, LREE-rich eudialyte from “migmatitic” grennaite.
This study supports the field and analytical evidence that there are varying types of eudialyte which can, to an extent, be differentiated by colour with the more vibrant pink variety being poor in REOs and the duller, brownish-red varieties containing higher values of REOs.
Summary:
Open pit operations are planned to be conventional diesel hydraulic shovel and truck extraction, with drill and blasting of final benches at 20 m height. The mine life has been designed at 20 years. There is pre-stripping required of 600 kt waste and 60 days have been allocated for this task. The life of mine (LOM) mining rate averages 1.15 Mt/a ore and 0.84 Mt/a waste.
The mine plan has been developed using owner operated equipment in all aspects of mining. Hauling is scheduled to operate on a single eight hour shift per day, five days a week. This equates to 241 operating calendar days, less five days for weather delays. Blast hole drilling operates on two eight hour shifts at the same operating days due to drilling requirements. It has been assumed there will be 85 % operating availability of equipment.
Blast fragmentation was required to meet a maximum of 600 mm for a planned crusher and the blast design was made to ensure fly rock does not affect the E4 highway located to the west.
Blast hole drilling will be completed with a track mounted blast hole drill, such as an Atlas Copco Flex Roc D60. Final bench heights will be 20 m, fired in two lifts. Owing to the bulk nature and similarity of ore and waste, a blasting pattern has been designed for use in all materials. Vertical 110 mm (4.3”) diameter holes at a 2.75 m x 3.25 m staggered pattern are planned with 0.37 m sub-drill and 2.75 m stemming.
The overall blast design has a tight pattern with relatively small hole diameters and increased stemming, this is due to the fragmentation and fly rock constraints, whilst meeting targeted powder factors for the rock mass.
Loading will be undertaken using a hydraulic shovel and large wheel loader as a back-up. The primary excavator will be a 100 tonne class unit with a 6.7 m3 bucket, such as the Komatsu PC1250-8. The shovel has been planned in a face shovel configuration as this will allow good operator visibility, selectivity, and allow the unit to scale loose blocks either reaching upwards or downwards on the 20 m bench.
The wheel loader is planned for auxiliary tasks such as muck pile loading and bench clean ups, as well as acting as another loading unit in case of mechanical down time on the primary hydraulic excavator. The wheel loader will have a 6.9 m3 bucket, such as a Volvo L250G; this is sized to match 55 tonne payload trucks.
Haulage will be done using 55 tonne class haul trucks. CAT 773G (55.3 t, 35.8 m3 capacity) rigid body haul trucks were planned with the excavating units and for haulage profiles. Oversize or unmanageable blocks will be separated by the hydraulic excavator then transported using the wheel loader to a separate area.
Mining haul ramps are designed at 10 % gradient and at 18 m width, a rolling resistance of 2 % has been assumed (2 % is equivalent to a hard, smooth surface stabilised surface, watered and maintained). Although the haul trucks are capable of descending at over 50 km/h, a site speed limit for heavy plant of 30 km/h on ramps and 40 km/h on the flat is recommended. The mine model has set the haul truck descending speed to match the inclined speed to ensure a constant cycle, thus avoiding trucks waiting to be loaded.
Processing
- Sulfuric acid (reagent)
- Calcining
- Magnetic separation
- Leaching & Solvent Extraction (SX)
Flow Sheet:
Summary:
An apron feeder will reclaim Run of Mine (ROM) material from the ROM bin onto a vibrating grizzly screen. Oversize material reports to a jaw crusher where the material is comminuted before recombining with the grizzly screen undersize and fed to the secondary crushing screen. Similarly, oversize from the secondary crushing screen will report to the secondary cone crusher where the material will be comminuted before reporting to the tertiary crushing screen. Screen undersize from the secondary and tertiary screens will then be transferred to the fine ore bin. Oversize material from the tertiary crushing screen will report to a tertiary crusher where it will be comminuted before being recycled to the tertiary crushing screen for classification. All material transfers between process units will be by conveyors.
Discharge from the fine ore bin will be delivered for primary grinding, via a conveyor, to an open circuit rod mill. Rod mill discharge will be screened with the oversiz ........

Recoveries & Grades:
Commodity | Parameter | Avg. LOM |
Total Rare Earth Oxides
|
Head Grade, %
| 0.59 |
Projected Production:
Commodity | Units | LOM |
Total Rare Earth Oxides
|
kt
| 102 |
All production numbers are expressed as concentrate.
Operational Metrics:
Metrics | |
Stripping / waste ratio
| 0.69 * |
Annual mining capacity
| 1.15 Mt of ore * |
Waste tonnes, LOM
| 16,679,072 t * |
Ore tonnes mined, LOM
| 23,570,526 t * |
Total tonnes mined, LOM
| 40,249,598 t * |
Tonnes processed, LOM
| 22,648,933 t * |
* According to 2015 study.
Reserves at January 13, 2015:
Category | Tonnage | Commodity | Grade |
Probable
|
23,571 kt
|
Total Rare Earth Oxides
|
0.592 %
|
Probable
|
23,571 kt
|
Heavy Rare Earth Oxides
|
0.314 %
|
Indicated
|
31,109 kt
|
Total Rare Earth Oxides
|
0.61 %
|
- Subscription is required.
Corporate Filings & Presentations:
- Subscription is required.
News:
Aerial view:
- Subscription is required.