Overview
Stage | Production |
Mine Type | Open Pit |
Commodities |
|
Mining Method |
|
Production Start | ...  |
Mine Life | 2030 |
Initial production from the Surubim open pit occurred in Q4 2021, including the processing of ore stockpiled during pre-stripping. The Surubim Mine is expected to contribute to higher throughput volumes and lower average processed copper grades at the MCSA Mining Complex in 2022. |
Source:
p. 10-11

Ero Copper Corp. (“Ero Copper, “Ero” or the “Company”) is a Vancouver-based copper mining company whose primary asset is a 99.6% interest in Mineração Caraíba S.A. (“Mineração Caraíba” or “MCSA”), a Brazilian mining company operating in the Curaçá Valley, northeastern Bahia State, Brazil.
Within the mining concessions, MCSA holds 100% legal and beneficial ownership.
Contractors
- Subscription is required.
Deposit Type
- Intrusion related
- Vein / narrow vein
Summary:
The Surubim District, containing the Surubim OP Mine and Surubim UG Mine, located at 9°34’12”S and 39°51’52”W, also includes the C-12 OP/UG Mine, located at 9°34’44”S and 39°52’27”W, the Lagoa da Mina project, located at 9°30’13”S and 39°47’48”W adjacent to the past producing Angicos Mine, the Cercado Velho project, located at located at 9°30’36”S and 39°47’52”W and the Terra do Sal project, located at 9°38’1”S and 39°49’6”W.
The Surubim district is located in the central part of the Curaçá Valley. The C12 deposit is located 1.2 km to the SW of the Surubim mine. The Cercado Velho and Lagoa da Mina deposits are at approximately 10 km to the NE of Surubim whereas the Terra do Sal deposit is situated 8 km to the SE of Surubim. The Surubim and C12 deposits are hosted in the Surubim gneiss (alternating tonalitic and granorioditic bands with gabbro and diorite bands) whereas the other three deposits are hosted in the Caraíba gneissic complex (biotite orthogneiss with local migmatite). The geology of the Surubim and C12 deposits consists of large gabbro-dominant units with minor pyroxenite units and remnants of gneiss that are at least 400mwide. In both deposits, the mafic-ultramafic units are intruded by late north-striking granite and pegmatite dykes. The geology of the Cercado Velho, Lagoa da Mina and Terra do Sal consist of orthogneiss and migmatites intruded by ultramafic units measuring a few centimeters up to 15m thick.
In all the deposits, the mafic-ult ........

Summary:
The Surubim and C12 OP mines are currently have been restarted their operating activities since Q4 2021.
The open pit operations of Surubim and C12 OP Mine in the Surubim District utilize conventional open pit mining, implementing proven drilling, blasting and loading / haulage equipment and technologies used in prior open pit operations within the Curaçá Valley by the Company.
To prepare sulphide copper ore for mining, the waste material located in the upper portion of the deposits (mostly comprised of waste rock and oxidized mineralization) is stripped mechanically by a bulldozer. While variable, the weathered profile is, on average, 15m to 20m in thickness throughout the Curaçá Valley. Waste material generated during stripping is stacked outside of the pit area, following the technical and environmental recommendations for each open pit mine.
After pre-stripping, hard rock mining of both barren waste and ore comprising the mineral reserves will be carried out by blasting with explosives. Primary rock drilling will be performed using hydraulic drills rigs with 127mm diameter blast holes, and a 2.40m x 4.80m staged mesh. The explosives, blasting agents and blasting accessories will be supplied by a licensed explosive supplier, readily available in the Curaçá Valley as demonstrated by the Company’s existing operations.
Ore and waste will be loaded by hydraulic backhoes with bucket capacities of 4.5 tonnes and transported from the o ........

Flow Sheet:
Three-stage crushing is used to prepare a nominal 12.5mm top size crushed feed for the ball milling circuit that also feeds the regrind mill circuit prior to being sent to flotation for the recovery of copper-bearing minerals.
There are two primary crushing operations. Ore from open pit mining is delivered to the surface primary cone crusher, featuring a nominal capacity of 1,600t/h. Feed enters the primary crushing operations with maximum size of 48” and is discharged with maximum size of 10”.
The blended product of the primary crushing operations is transported via conveyors to a feeder stockpile with a capacity of 12,000 tonnes. The stockpile feeds two primary double deck screens, configured with 100mm aperture on the top and 40mm aperture on the bottom decks. The material over 40mm feeds one of two secondary cone crushers (seven-feet (“ft.”) standard Symons; 1,400t/h of capacity each) set to 28mm aperture. Screen undersize and secondary crushers products discharge onto one conveyor in an open circuit configuration.
Secondary cone crusher discharge and primary screen fines are blended with tertiary crusher discharge and are conveyed to the seven secondary double screen decks, configured with 25mm aperture on the top and 16mm aperture on the bottom decks. Tertiary crushing is performed with four standard CH660 Sandvik cone crushers (capacity of 350t/h each) set to 20mm aperture. Oversize material passes to the tertiary crushers operating in a closed-circuit configuration. Final product from the combined crushing and screening operations is 88% passing 1/2”.
Crushed ore is conveyed to the stacker-reclaimer system to further homogenize the ore for feeding the plant. The stacker-reclaimer system is comprised of a two-armed stacker and a 16 bucket-wheel reclaimer with capacities of 1,600t/h and 1,200t/h, respectively. Crushed ore capacity of the stacker-reclaim system is currently 140,000 tonnes.
GRINDING
The grinding circuit consists of two identical lines operating with a primary ball mill operating in closed circuit with a dedicated battery of 26” hydro-cyclones. Each ball mill is 5.0 m by 7.6 m, charged with 90 mm in diameter high chrome cast steel balls. The nominal grinding capacity of each mill is 200 t/h each. Typical ball consumption is 340 g/t.
Blended ore from the stacker reclaimer is withdrawn through belt feeders below one of the 3,000 tonne ore silos that are interconnected. Ore is delivered to the ball mill over a belt weightometer to control and measure the mass of ore sent to each mill for metallurgical accounting purposes.
The coarse fraction from the cyclone underflow recycles to the ball mill feed chute for further grinding. Overflow from both grinding lines combines as feed to the high frequency screeners and regrinding circuit.
HIGH FREQUENCY SCREENS AND REGRINDING CIRCUIT
The cyclone oversize is pumped to high frequency screening operations comprised of eight screens with five decks each of 105+ micron aperture. The high frequency screening coarse fraction is gravity fed to the vertical mill (STM HIG Mill HIG2300/23000) for regrinding, operating in an open circuit. The HIG Mill (High Intensity Grinding mill) was commission in September 2020. The screening operation fines combine with the regrind mill product and are pumped to the flotation.
Flow Sheet:
Summary:

- subscription is required.
Combined production numbers are reported under
Caraíba (MCSA) Operation
Operational Metrics:
Metrics | 2019 | 2018 | 2017 |
Total tonnes mined
| 727,578 t | 4,096,723 t | 3,508,430 t |
Annual mining rate
| | 0.8 Mt | |
Ore tonnes mined
| | | 994.8 kt |
Daily ore mining rate
| | | 3,000 t |
Reserves at October 1, 2020:
Reported Mineral Reserves and Resources estimation has not changed on 12/31/2021.
Category | OreType | Tonnage | Commodity | Grade | Contained Metal |
Proven
|
In-Situ (OP)
|
2,778 kt
|
Copper
|
0.82 %
|
23 kt
|
Proven
|
In-Situ (UG)
|
513 kt
|
Copper
|
1.09 %
|
6 kt
|
Probable
|
In-Situ (OP)
|
123 kt
|
Copper
|
0.55 %
|
1 kt
|
Probable
|
In-Situ (UG)
|
515 kt
|
Copper
|
0.83 %
|
4 kt
|
Measured & Indicated
|
In-Situ (OP)
|
7,130 kt
|
Copper
|
0.8 %
|
56.9 kt
|
Measured & Indicated
|
In-Situ (UG)
|
4,904 kt
|
Copper
|
0.96 %
|
47 kt
|
Inferred
|
In-Situ (OP)
|
1,413 kt
|
Copper
|
0.2 %
|
2.8 kt
|
Inferred
|
In-Situ (UG)
|
4,482 kt
|
Copper
|
0.92 %
|
41.3 kt
|
Operating Costs:
| Units | 2021 | 2019 | 2018 | 2017 |
OP mining costs ($/t mined)
|
BRL
| 10.5 | 11.7 | 15.4 | 12.7 |
HME Type | Model | Size | Quantity | Leased or Contractor | Ref. Date |
Backhoe
|
|
|
.......................
|
|
Oct 1, 2018
|
Bulldozer
|
.......................
|
|
.......................
|
|
Oct 1, 2020
|
Drill
|
.......................
|
|
.......................
|
|
Oct 1, 2020
|
Truck (haul)
|
|
70 t
|
.......................
|
|
Oct 1, 2020
|
Truck (haul)
|
|
35 t
|
.......................
|
|
Oct 1, 2020
|
- Subscription is required.
Corporate Filings & Presentations:
- Subscription is required.
- Subscription is required.