Overview
Stage | Permitting |
Mine Type | Open Pit |
Commodities |
|
Mining Method |
|
Processing |
- Smelting
- Filter press plant
- Carbon re-activation kiln
- Heap leach
- Carbon in column (CIC)
- Carbon adsorption-desorption-recovery (ADR)
- Electrorefining
- Solvent Extraction & Electrowinning
- Cyanide (reagent)
|
Mine Life | 16 years (as of Jan 1, 2021) |
Latest News | Rio2 Provides Update of Fenix Gold Environmental Assessment Process June 23, 2022 |
Source:
p. 10
Company | Interest | Ownership |
Rio2 Ltd.
|
100 %
|
Indirect
|
Rio2 is a precious metals exploration and development company with a portfolio of Chilean and Peruvian projects including the flagship 100%-owned Fenix Gold Project. Rio2 owns and controls the Project through its Chilean subsidiary, Fenix Gold Limitada.
Deposit Type
- Vein / narrow vein
- Breccia pipe / Stockwork
- Intrusion related
- Epithermal
Summary:
Gold mineralization is considered to represent an intrusion-related, low-sulphidation, quartzsulphide, Au and Cu deep epithermal system. These systems often host very fine (refractory) gold in sulphides.
Diatreme flow dome complexes vent to the surface and in all other cases host epithermal Au mineralization, locally cutting or telescoped over older porphyry manifestations.
Rather, the dominance of massive chalcedony in these veins is more typical of formation in an epithermal environment. Petrology work (Lohmeier, 2017) describes bornite replaced by chalcopyrite along with sphalerite (of unknown Fe:Zn ratio) and tetrahedrite as the sulphide minerals, typical of an intrusion-related fluid in a deep epithermal setting. Lohmeier (2017) also recognized a correlation between Au and Ag-Bi-Cu, typical of a low sulphidation deep epithermal geochemical signature.
While any possible association between Au and magnetite is unusual, the final event of quartz- pyrite mineralization is most certainly typical of the intrusion-related low sulphidation quartz- sulphide Au + Cu deep epithermal style.
Overprinting magmatic events include pre-mineral andesite domes, followed by emplacement of polyphasal dacite dome (including some transitional to andesite in composition) and associated diatreme (milled matrix) breccia events. The mineralization of low sulphidation Au is best developed in sheeted quartz veins, breccia clasts and very finely disseminated with a possible supergene component (Corbett, 2019).
Mineralization at the Fenix Gold Project straddles a regionally significant northwest trending structural zone, and mineralization is typically hosted in northwest trending structures.
Three structural systems have been defined at the Project; a northwest fault system, a tensional east-west system, and a late northeast fault system:
- The northwest fault system consists of three principal sub-parallel northwest striking faults which cross cut the northern portion of Fenix Central and Fenix North zones. Dips are vertical to sub-vertical. Strike slip movement partially controls the location of intrusions and mineralization.
- The East-West system is tensional from the NW system. Locally, the EW system is controlling the emplacement of the Black Banded Veins, which are associated with the gold mineralization.
- Post mineralization, sub-vertical northeast trending normal faulting that has divided mineralization into three blocks (Fenix North, Fenix Central and Fenix South).
Oxide-gold mineralization extends northwest over 2.5 km of strike and up to 600 m across strike. Drilling has traced oxide-gold mineralization to 600 m below surface and the resource remains open.
Microscope studies indicate that gold mineralization primarily occurs within black and grey banded veinlets (BBV and GBV) in the breccia complex and the dacitic dome, and secondarily within early chlorite-magnetite-quartz veinlets.
Gold mineralization may be encountered in phreatomagmatic breccia, surrounding hydrothermal breccia, in dacite porphyry and surrounding andesitic dikes and plugs.
Sheeted banded quartz veins vary from white to black/grey bands. The white vein portions comprise bands of massive chalcedony and saccharoidal to fine crystalline quartz. Crystalline quartz is deposited from a cooling fluid and is not an indication of temperature of formation. Vein margins are sharp although wavy coliform dark bands are similar to some epithermal veins.
The dark bands display only local magnetic character, but the dark colour results from most abundant secondary inclusions (Lohmeier, 2017), in a manner similar to other sheeted banded veins in the Maricunga Belt (Muntean and Einaudi, 2000). In hand specimen, higher Au grade mineralization is clearly associated with these veins, which may occur as submicroscopic free Au particles within the dark coloured inclusion-rich bands.
Summary:
The Fenix Gold Project consists of an open pit mine which will be developed using conventional drill and blast techniques, with an excavator and truck configuration. The mining rate is 20,000 tpd of ore to the crusher, with low-grade to one of two stockpiles, and waste to the waste dump. The mining rate has been determined based on the processing rate, which is primarily a function of the available water. The water supply will be delivered to site by a fleet of trucks from Copiapo. The water supply rate was determined primarily by assessing the practical and sustainable limit to the number of trucks that can make the continual cycle from Copiapo to the mine.
For this mining rate and cost structure, the cut-off grade was determined using Whittle software to be 0.24 g/t Au. To further improve the economics and increase cash flow, a medium grade and lowgrade stockpile will be used. The medium grade material is between 0.30 – 0.4 g/t Au and lowgrade material is between 0.24 – 0.30 g/t Au. Both stockpiles will be located adjacent to the crusher, however the low-grade stockpile will be located close to the pad and maybe treated directly as ROM mineral if metallurgical work indicates an acceptable recovery.
The first year of production has an average production rate of 12,000 tpd of material placed on the leach pad, which reflects the ramp up from 0 to 20,000 tpd. This is due to the starter pit initial phases being located on topographic high points where there is limited work space. The mined grade is 0.76 g/t producing 80 koz of recovered gold.
Mining operates at the full 20,000 tpd capacity between years 2 and 13, and if required, minor top up from stockpiles will ensure that the mine operates at the total mining rate (ore and waste), set at 20.5 Mtpa. The grade mined during this period is 0.536 g/t Au recovering an average of 94.4 koz each year.
Between years 12 and 13 approximately 30% of production is rehandled from the low and medium grade stockpiles to achieve a 20,000 tpd processing rate, and between years 14 to 17 feed to pad is from 100% stockpile rehandle, with an average grade of 0.285 g/t Au recovering an average 39.6 koz from the leach pad each year.
The final pit was designed with ramp widths of 14 m in accordance with width requirements of the Chilean mining regulations. Pit ramps have a gradient of 10% for two-way traffic haul road.
Mine Design Parameters (Mining-plus):
- Haul Road Width - 14 m;
- Haul Road Gradient - 10%;
- Bench Height - 10 m;
- Stacked Bench Height with 2 Benches Stacked - 20 m;
- Nominal Minimum Mining Phase Width - 50 m;
- Batter Angle - 75°;
- Berm Width - 9.5 m;
- Inter-ramp Angle - 53°;
- Safety Berm Width Every 160 vertical m - 30 m.
The Pit will be drilled and blasted on 10 m high benches using 155 or 171 mm diameter blast holes and a powder factor of 0.42 - 0.61 Kg/bcm (kilograms per bank cubic meter). Loading of ore and waste would be with 70 t – 90 t excavators into 43 t payload rigid frame 8m x 4m heavy tipper dump trucks. Ore will be hauled to the primary crusher and waste is hauled to the waste dump.
So proposed mining will be conducted in 20 m benches with double blasting (2 x 10 m) to minimize dilution and ore losses. The operative bench height is in the order of 11-12 m due to the swell factor applied after the blasting.
Flow Sheet:
Crusher / Mill Type | Model | Size | Power | Quantity |
Gyratory crusher
|
.......................
|
42' x 63'
|
|
|
Summary:
The mineral from the mine (ROM) will be transported by 43 t capacity trucks (Actros or Volvo type) to the feed hopper of the primary gyratory crusher (Metso 42' x 63', or equivalent) at a rate of 1,111 t/h with an availability of 75% (18 hours per day of operation). The feed is crushed to a P80 size of 4”. The feed will then pass to the crusher discharge hopper from where it will be discharged by an apron feeder to a short sacrificial conveyor. This conveyor will transfer the feed to conveyor No. 1 that will transport the crushed mineral to the stockpile. An electromagnet will be located on the sacrificial belt to collect tramp metal from the mine. A rock breaker will be installed at the primary crusher feed hopper to break oversize rocks and prevent blockages in the crusher. A dust suppression spray system will be installed at the crusher feed hopper to reduce the amount of dust in the atmosphere.
The crushed feed is transported by conveyor No. 1 to a stockpile, which will have a total storage capacity of approximately 30,000 t. Lime will be added to conveyor No. 1 at a rate of 4.0 kg/t of feed using a variable speed screw feeder. The stockpiled material is loaded by front-end loaders into trucks for transport to the leach pads.
The lime is delivered to the mine in dry bulk carrier trucks. The lime is transferred pneumatically from the trucks to two 200 t capacity lime storage silos. Each silo will be equipped with an activator that will supply a continuous flow of lime to the screw feeder that will dose the lime onto conveyor belt No. 1.
Processing
- Smelting
- Filter press plant
- Carbon re-activation kiln
- Heap leach
- Carbon in column (CIC)
- Carbon adsorption-desorption-recovery (ADR)
- Electrorefining
- Solvent Extraction & Electrowinning
- Cyanide (reagent)
Flow Sheet:
Summary:
The Fenix Gold Project has approximately 116 million tonnes of ore with an average grade of 0.49 g/t Au, which will be processed at a maximum rate of 20,000 tpd (7.3 million tonnes per year), giving a life of mine of approximately 16 years.
The results of the metallurgical test work carried out between 2010 and 2017 show that the mineral in the Fenix Gold Project is amenable for the recovery of gold by heap leaching.
The mineral will be mined by open pit methods; it will be crushed to 80% passing 4” in a primary crushing circuit and transported in trucks to heap leach pads with a lift height of 10 m. The feed will be leached with a dilute sodium cyanide solution and the gold will dissolve, the gold will be recovered from the pregnant leach solution (PLS) in an adsorption circuit with activated carbon and then recovered in pressure desorption and electro-deposition circuits. The electrolytic precipitate will be filtered and sent to a retort furnace and finally smel ........

Recoveries & Grades:
Commodity | Parameter | Avg. LOM |
Gold
|
Recovery Rate, %
| 75 |
Gold
|
Head Grade, g/t
| 0.49 |
Projected Production:
Payability Gold is 100.0%
Commodity | Product | Units | Avg. Annual | LOM |
Gold
|
Metal in doré
|
koz
| 85 | 1,371 |
Gold
|
Payable metal
|
koz
| | 1,371 |
Operational Metrics:
Metrics | |
Stripping / waste ratio
| 0.81 * |
Daily ore mining rate
| 20,000 t * |
Waste tonnes, LOM
| 93,549 kt * |
Ore tonnes mined, LOM
| 115,040 kt * |
Daily processing capacity
| 20,000 t * |
Tonnes processed, LOM
| 115,040 kt * |
Annual processing capacity
| 7.3 Mt * |
Annual mining rate
| 20.5 Mt * |
* According to 2019 study.
Reserves at August 15, 2019:
Mineral Reserve cut-off grade - 0.24 g/t Au.
Mineral Resource cut-off grade - 0.15 g/t Au.
Category | Tonnage | Commodity | Grade | Contained Metal | Recoverable Metal |
Proven
|
53 Mt
|
Gold
|
0.52 g/t
|
866 koz
|
650 koz
|
Probable
|
63 Mt
|
Gold
|
0.47 g/t
|
962 koz
|
722 koz
|
Proven & Probable
|
116 Mt
|
Gold
|
0.49 g/t
|
1,828 koz
|
1,372 koz
|
Measured
|
122.4 Mt
|
Gold
|
0.41 g/t
|
1,630 koz
|
|
Indicated
|
288.3 Mt
|
Gold
|
0.36 g/t
|
3,355 koz
|
|
Measured & Indicated
|
410.7 Mt
|
Gold
|
0.38 g/t
|
4,985 koz
|
|
Inferred
|
136.6 Mt
|
Gold
|
0.32 g/t
|
1,388 koz
|
|
Corporate Filings & Presentations:
- Subscription is required.
News:
News | Date |
Rio2 Provides Update of Fenix Gold Environmental Assessment Process
|
June 23, 2022
|
Rio2 Receives US$25m First Deposit From Fenix Gold Stream
|
March 29, 2022
|
Rio2 Raises US$5M On Sale Of Non-Core Assets
|
December 23, 2021
|
Rio2 Announces Signing of US$50 Million Gold Stream with Wheaton Precious Metals on the Fenix Gold Project
|
November 16, 2021
|
Rio2 Raises C$35.1 Million Through Public Offering And Private Placement
|
August 11, 2021
|
Rio2 Files Final Financing Prospectus
|
August 5, 2021
|
Rio2 Selects Run-of-Mine Leaching for the Fenix Gold Mine
|
June 22, 2021
|
Rio2 Obtains Surface Rights for the Construction and Operation of the Fenix Gold Project
|
October 26, 2020
|
Rio2 Engages Financial Advisor for Fenix Gold Project Construction Financing
|
October 21, 2020
|
Rio2 Designates Process Plant Construction and Civil Contractors for the Fenix Gold Project
|
September 28, 2020
|
Rio2 Designates STRACON as the Lead Mining Contractor for the Fenix Gold Project
|
July 7, 2020
|
Rio2 Strengthens the Fenix Gold Project Team as it Moves Closer to Construction
|
May 19, 2020
|
Rio2 Limited Files Technical Report for the Fenix Gold Project Updated Pre-Feasibility Study
|
October 17, 2019
|
Rio2 Limited Completes Updated Pre-Feasibility Study for the Fenix Gold Project in Chile
|
September 4, 2019
|
Rio2 Limited Drills 148m @ 0.78 g/t Au and 44m @ 1.26 g/t Au at the Fenix Gold Project, Chile
|
March 21, 2019
|
Rio2 Limited Drills 192m @ 0.81 g/t Au and 124m @ 0.77 g/t Au at the Fenix Gold Project, Chile
|
January 22, 2019
|
Aerial view:
- Subscription is required.