Beruang Kanan Main (BKM) Project

This page is not tailored to
devices with screen width under 750 px.
 Location:
169 km NW from Palangkaraya, Indonesia

  Project Contacts:
Jl Teuku Umar 32A
Palangkaraya
Indonesia
73112
Phone  ...  Subscription required
WebsiteWeb
Additional Resources for Suppliers & Investors
Drill results over 30 g/t Au
Stay on top of recent discoveries.
Search drill results by commodity and grade.
Largest mines in the Americas
Mining and mill throughput capaciites.
Full profiles of select mines and projects.
Deepest underground mines
Shaft depth and mill throughput data.
Full profiles of select mines and projects.
Heavy mobile equipment
HME type, model, size and quantity.
Full profiles of select mines and projects.
Permitting and construction projects
Projects at the permitting or construction stage. Full profiles of select projects.
Mines with remote camps
Camp size, mine location and contacts.
Full profiles of select mines and projects.
Mines & projects in Indonesia
A list of country's mines and projects.
Full profiles of select mines and projects.
  • Overview
  • Owners
  • Geology
  • Mining
  • Processing
  • Production
  • Reserves
  • Costs & Financials
  • Fleet
  • Personnel
  • Filings & News

Thank you for browsing through mine profiles compiled by the Mining Data Online team.

Would you like to subcribe or schedule a Demo?
  • Name:
     
  • Company:
     
  • Position:
     
  • Phone:
  • Email:
  • Message:

Overview

StagePermitting
Mine TypeOpen Pit
Commodities
  • Copper
Mining Method
  • Truck & Shovel / Loader
Processing
  • Sulfuric acid (reagent)
  • Heap leach
  • Solvent Extraction & Electrowinning
Mine Life8.83 years (as of Jan 1, 2019)
Latest NewsAsiamet Resources Ltd.: Important Environmental Approval Received for BKM Copper Project     January 4, 2021


Owners

Source: p. 30
CompanyInterestOwnership
Asiamet Resources Ltd. 100 % Indirect
PT Kalimantan Surya Kencana 100 % Direct
PT Kalimantan Surya Kencana (KSK, incorporated in Indonesia) is the 100% owner of the 6-th generation Contract of Work (KSK CoW) within which BKM is located. KSK in turn is owned 75% by Indokal Limited (incorporated in Hong Kong) and 25% by PT Pancaran Cahaya Kahayan (incorporated in Indonesia). Indokal Limited owns 99% of PT Pancaran Cahaya Kahayan with the remaining 1% owned by Mr. Mansur Geiger (held in trust for Asiamet Resources Limited). The parent company to the corporate structure is a Bermuda company, Asiamet Resources Limited (AMR), formally Kalimantan Gold Corporation Limited, which is a publically listed company on the AIM (London) stock exchange. AMR owns 100% of the shares in Indokal Limited.

Deposit Type

  • Porphyry
  • Epithermal
  • Vein / narrow vein


Summary:

Subsequent exploration and evaluation of the KSK CoW has centred on four primary areas (Baroi, Beruang Tengah, Beruang Kanan and Mansur), where activities have focused on identifying porphyry and related epithermal styles mineralisation.

At the Beruang Kanan Main Zone deposit copper is the only element of economic interest, occurring as chalcocite, covellite, bornite and chalcopyrite replacement of pyrite in veins and less common fracture fill settings. The BKM deposit is structurally controlled and has been delineated as:

• twenty five laminated stacked and adjacent domains dipping on average easterly at 30 degrees (10 to 45 degrees dips) over a northerly strike length of 1,300m, across a total width of 900m and a vertical extent of 450m;
• centred on three areas whose lateral and vertical extents are well defined; and
• having extensive and intense alteration throughout the mineralised zone.


Copper mineralisation at BKM remains open in several areas and exploration in the wider district remains in its infancy with:

• structural interpretation indicates potential for repeat settings to exist at depth and in laterally detached nearby locations, although not yet supported by deeper drill holes.
• geological observations during field mapping and geochemical data from drill core, surface rock chip samples at Beruang Kanan South and Beruang Kanan West prospects indicate near surface and similar style copper mineralisation, highlighting the potential for the development of additional copper mineralisation adjacent to the project, with recent drilling confirming similar style mineralisation.
• obvious drill targets with potential for the discovery of additional copper and polymetallic resources also exist nearby BKM and within the wider KSK CoW.


Mining Methods

  • Truck & Shovel / Loader


Summary:

Pits were designed as a close match to the Enterprise Optimisation stage and final pit shells. The pit development stages include:

• initial roads to provide access to the waste rock dump in a valley running west of the pit and the ROM stockpile and crusher east of the pit;
• shallow starter pits in the south and north of the deposit which cut into the eastern face accessing high grade, predominantly chalcocite ore;
• an intermediate stage pit in the north which assists with continuity of ore supply; and
• pushbacks to the final pit in the south and north of the deposit.

The Enterprise Optimisation work and subsequent pit designs and schedules included Measured and Indicated Resources as well as Inferred Resources. The Measured and Indicated Resources account for 93% of copper cathode produced. The Inferred Resource material is mined almost exclusively towards the end of the mine life and accounts for 7% of copper cathode produced. Inferred Resources have not been included in the Ore Reserves.

The mining operations consist of:
• open cut mining operation utilising 300t hydraulic excavators, 100t trucks and ancillary equipment;
• mining activities conducted by a mining contractor; and
• mine planning, grade control sampling, modelling and production scheduling conducted by the
Company.

Other key aspects of the mining operation include:
• average mine operating costs over the mine life are $1.98 per tonne of ore and waste. This cost aligns with actual costs from a comparable scale operating open cut gold mine in Central Kalimantan;
• drill and blast – blast hole patterns and areas of free dig are based on material types in the resource model;
• grade control – sampling assumed to be from blast holes;
• slope stability – the design wall slopes assume dewatering by drilling horizontal drain holes into the pit walls;
• a requirement that all benches and berms be drained to prevent rain water seeping back into the walls;
• pit roads and benches – high rain fall and potential rock degradability in some areas of the pit will make it necessary maintain a source of surfacing material for pit benches and ramps;
• pit water management – slope stability and acid drainage issues make it necessary to capture rain fall and wall seepage in the pit area as quickly as possible for neutralisation in facilities adjacent to the pits; and
• acid waste rock management – most of the leach feed and waste is expected to be pyritic and potentially acid forming. Allowance is made for compaction of all waste in the waste rock dump to minimise seepage through the dump.


Crushing and Grinding

Processing and plant facilities details include a three-stage ore crushing circuit (with primary and secondary sizers and two parallel tertiary impact crushers.


Processing

  • Sulfuric acid (reagent)
  • Heap leach
  • Solvent Extraction & Electrowinning

Flow Sheet: Subscription required

Summary:

The BKM process infrastructure is based on a tertiary crushed ore stacked in a Valley Fill Heap Leach, with conventional SX-EW technology. There is an additional requirement for a neutralisation facility to deal with the excess of acidic water generated due to the site wide positive water balance.

Processing and plant facilities details include:
• a three-stage ore crushing circuit (with primary and secondary sizers and two parallel tertiary impact crushers);
• an ore agglomeration to facilitate fines stabilisation and pre-conditioning of the ore with sulphuric acid and raffinate;
• leach pad stacking consists of portable ramp (“grasshopper”) conveyors and a radial stacker with a stinger. This will allow agglomerated ore to be stacked in lifts up to 10m high;
• a valley fill heap leach that is designed to allow for 7 lifts each of 10m to accommodate the Life of Mine stacked ore of 57Mt. It is completed with an engineered initial platform with a composite ........

Recoveries & Grades:

CommodityParameterAvg. LOM
Copper Head Grade, % 0.39

Projected Production:

CommodityUnitsAvg. AnnualLOM
Copper kt 20173
All production numbers are expressed as cathode.

Operational Metrics:

Metrics
Stripping / waste ratio  ......  Subscription required
Waste tonnes, LOM  ......  Subscription required
Ore tonnes mined, LOM  ......  Subscription required
Total tonnes mined, LOM  ......  Subscription required
Tonnes milled, LOM  ......  Subscription required
Annual production capacity  ......  Subscription required
* According to 2019 study.
Subscription required - Subscription is required.

Reserves at June 14, 2019:
The 0.2%Cu grade reporting cut approximates the mineralised domains extents.

CategoryTonnage CommodityGradeContained Metal
Proven 21.1 Mt Copper 0.6 % 137 kt
Probable 30.4 Mt Copper 0.5 % 166 kt
Proven & Probable 51.5 Mt Copper 0.6 % 303 kt
Measured 20.6 Mt Copper 0.7 % 148.5 kt
Indicated 34.1 Mt Copper 0.6 % 212.6 kt
Inferred 15 Mt Copper 0.6 % 90.8 kt
Total Resource 69.6 Mt Copper 0.6 % 451.9 kt

Commodity Production Costs:

CommodityUnitsAverage
All-in sustaining costs (AISC) Copper USD  ......  Subscription required *
C1 cash costs Copper USD  ......  Subscription required *
Assumed price Copper USD  ......  Subscription required *
* According to 2019 study / presentation.
Subscription required - Subscription is required.

Operating Costs:

Units2019
OP mining costs ($/t mined) USD 1.98 *
OP mining costs ($/t milled) USD  ......  Subscription required
Processing costs ($/t milled) USD  ......  Subscription required
* According to 2019 study.
Subscription required - Subscription is required.

2019 Study Costs and Valuation Metrics :

MetricsUnitsLOM Total
Initial CapEx $M USD  ......  Subscription required
Expansion CapEx $M USD  ......  Subscription required
Closure costs $M USD  ......  Subscription required
OP OpEx $M USD  ......  Subscription required
Processing OpEx $M USD 255.5
Site services costs $M USD 91
G&A costs $M USD 10.5
Total OpEx $M USD  ......  Subscription required
Royalty payments $M USD  ......  Subscription required
Gross revenue (LOM) $M USD  ......  Subscription required
EBITDA (LOM) $M USD  ......  Subscription required
After-tax Cash Flow (LOM) $M USD  ......  Subscription required
After-tax NPV @ 10% $M USD  ......  Subscription required
After-tax NPV @ 8% $M USD  ......  Subscription required
After-tax IRR, %  ......  Subscription required
After-tax payback period, years  ......  Subscription required
Subscription required - Subscription is required.

Proposed Heavy Mobile Equipment as of June 14, 2019:
HME TypeSizeLeased or
Contractor
Excavator 300 t Leased
....................... Subscription required ....................... Subscription required Leased
Subscription required - Subscription is required.

Mine Management:

Job TitleNameProfileRef. Date
....................... Subscription required ....................... Subscription required Subscription required Oct 13, 2020
Subscription required - Subscription is required.

Staff:

EmployeesContractorsTotal WorkforceYear
Subscription required Subscription required Subscription required 2019

Corporate Filings & Presentations:

DocumentYear
................................... Subscription required 2019
Technical Report 2017
Preliminary Economic Assessment 2016
Year-end Mineral Reserves 2015
Subscription required - Subscription is required.

News:

NewsDate
Asiamet Resources Ltd.: Important Environmental Approval Received for BKM Copper Project January 4, 2021