Stage | Production |
Mine Type | Tailings |
Commodities |
|
Mining Method |
- Truck & Shovel / Loader
- Hydraulic mining
|
Mine Life | 20 years (as of Jan 1, 2021) |
Source:
p. 59, 60

Effective 10 January 2020, the Group exercised its option to acquire an additional 12.05% in DRDGOLD. The consideration amounted to R1,085.6 million for the subscription of 168,158,944 additional new ordinary shares resulting in a 50.1% shareholding in DRDGOLD Limited (effective 50.66% after considering treasury shares held by DRDGOLD).
Contractors
- Subscription is required.
Summary:
The mineral assets are historical gold plant tailings material from the mining of auriferous and uraniferous ore from the goldbearing, late Archaean (2.7Ga to 3.2Ga), Witwatersrand Basin in the West Rand Goldfield. The typical composition is quartz (70 – 80%), mica (10%), chlorite and chloritoid (9% – 18%) and pyrite (1% – 2%). Gold, uranium oxide, zirconium and chromium are minor constituents.
The composition of a TSF depends on the geochemical make-up of the material being mined and the chemicals used in the mining and extraction process. Further, the internal structure of the TSF reflects the mining strategy and depositional methodologies employed for each operation. The bulk density of tailings material and the lateral and vertical variation in moisture content is a critical factor in the accurate estimation of tonnages. In addition, secondary processes such as metal re-mobilisation, erosion, weathering, leaching and acid mine drainage can affect the geochemical characteristics of a TSF. Gold can undergo mobilisation within the TSF over time, and hence, may exhibit areas of re-concentration, and even be present in the sub-structure (footprint) soil. These factors can result in a considerable variation in gold content and distribution throughout the TSF and such variation has an impact on final recoveries and projected revenues for the operation.
Mining Methods
- Truck & Shovel / Loader
- Hydraulic mining
Summary:
Hydraulic mining (hydro-mining) using high-pressure water cannons to hydraulically excavate tailings material. A second mining method employed by Ergo is the use of front-end loaders (FEL) to load slimes/sand. The FEL loads directly into a truck which then transports the ore to the processing plant.
Source:
Summary:

- subscription is required.
Production:
Commodity | Units | 2021 | 2020 | 2019 | 2018 |
Gold
|
koz
| ......  | ......  | ......  | 59 |
- Subscription is required.
Operational Metrics:
Metrics | 2021 | 2020 | 2019 | 2018 |
Tonnes milled
| ......  | ......  | 26,418 kt | 9,904 kt |
- Subscription is required.
Reserves at December 31, 2021:
Mineral Reserves cut-off 0.13 - 0.18 g/t for FWGR and 0.2 g/t for Ergo.
Category | Tonnage | Commodity | Grade | Contained Metal |
Proven
|
245 Mt
|
Gold
|
0.3 g/t
|
2.6 M oz
|
Probable
|
264 Mt
|
Gold
|
0.3 g/t
|
2.6 M oz
|
Proven & Probable
|
509 Mt
|
Gold
|
0.3 g/t
|
5.2 M oz
|
Measured
|
509 Mt
|
Gold
|
0.3 g/t
|
5.2 M oz
|
Indicated
|
579 Mt
|
Gold
|
0.2 g/t
|
4.6 M oz
|
Measured & Indicated
|
1,109 Mt
|
Gold
|
0.3 g/t
|
9.8 M oz
|
Inferred
|
22 Mt
|
Gold
|
0.2 g/t
|
0.2 M oz
|