The Gunnison Project is a low-cost, environmentally friendly in-situ recovery copper extraction project that is permitted to 125 million pounds per year of copper cathode production. Excelsior announced the start of construction in December 2018, and the completion of the construction phase in December 2019, including the wellfield drilling and the supporting infrastructure. Upgrades to the adjacent Johnson Camp mine (“JCM”) Solvent Extraction and Electrowinning (“SX-EW”) plant were also completed in December 2019. The injection of mining fluids to the wellfield for copper production started on December 31, 2019 and the Company began the start-up and commissioning phase of the project in January 2020. On April 9, 2020 a decision was made to place the project on Care and Maintenance in response to the COVID-19 global pandemic. On August 12, 2020 the Company announced that a small-scale restart had commenced. |