Greenstone Project is a multi-million-ounce gold project located in the top-tier mining jurisdiction of Ontario, Canada.
On October 27, 2021, Equinox Gold announced groundbreaking for full-scale construction.
Ore was introduced into the grinding circuit on April 6, 2024, with first gold pour expected in May 2024. More than 1.5 million tonnes of ore have been stockpiled and 70,000 tonnes of low-grade ore has been pre-crushed to use for early commissioning feed. Progressively higher-grade ore will be fed into the mill as production ramps up toward planned throughput of 27,000 tonnes per day, with commercial production targeted for Q3 2024. |