The current environmental permit limits the total Björkdal production capacity to 1.70 Mtpa. Prior to 2020, production was split between the underground mine and the open pit. In 2019, mining of the open pit was stopped for economic reasons and this mill feed was replaced with ore from the low grade stockpile and an increase in underground production.
The remaining open pit material remains economically viable, however, the low grade stockpile realizes more value, so open pit mining has been deferred for several years until the stockpile has been run-down and open pit production is required to offset reducing underground production.
As presently envisaged in the LOM plan, open pit pre-stripping and production will be restarted in 2026 to supplement the decrease in production from the underground mine.
Björkdal
Open Pit
Mine Design
During 2022, potential for expanding the current open pit at Björkdal was re-evaluated. Benches will be 5 m high, and are taken in groups of two to four with an 8 m to 10 m wide berm every 10 m to 20 m. A 72° to 85° bench face angle (BFA) is used to give an overall wall slope of 42° to 52°.
Mining Method
The open pit has currently been halted and is planned to be restarted in 2026, however, this could be delayed further in the event of additional underground reserves being identified. The planned mining method is standard truck and shovel mining, as was done historically. Details will b ........
