Overview
Stage | Production |
Mine Type | Open Pit |
Commodities |
|
Mining Method |
|
Processing |
- Gravity separation
- Intensive Cyanidation Reactor (ICR)
- Smelting
- Centrifugal concentrator
- Carbon re-activation kiln
- Agitated tank (VAT) leaching
- Carbon in pulp (CIP)
- Solvent Extraction & Electrowinning
- Cyanide (reagent)
|
On-Site Camp |
2,020 person |
Mine Life | 20 years (as of Jan 1, 2020) |
Detour Lake Mine is the second largest gold producing mine in Canada. |
Latest News | Kirkland Lake Gold Announces Filing of Detour Lake Technical Report, Including New Life-Of-Mine Plan March 31, 2021 |
Source:
p. 31
The Kirkland Lake Gold Ltd. obtained the Detour Lake Mine through the acquisition of Detour Gold on January 31, 2021
Deposit Type
- Vein / narrow vein
- Hydrothermal
Source:
p.71
Summary:
Two types of gold mineralization styles have been identified to date on the Property. The first, host to the bulk of mineralization in the Detour Lake area (Detour Lake and West Detour deposits), occurs as orogenic greenstone-hosted hydrothermal lode gold deposits. These deposits are typical of the AGB, and in particular the gold deposits found along the Destor-Porcupine Fault Zone from Timmins, Ontario through to Destor, Québec. These deposit types are found in greenstone belts around the world and are responsible for a large proportion of past world gold production, including most of the Canadian gold production.
A second style of gold mineralization was identified in the Lower Detour area, which is localized into three spatially related mineralized horizons known as Zones 58, 58N, and 75. These mineralized lenses share characteristics with both syenite-associated oxidized intrusion-related deposits of the Kirkland Lake area (Robert, 2001) and the Sigma-Lamaque deposits of the southern Abitibi (Robert, 1986), the latter of which are thought to be borne of the orogenic model described above. Still in the early stages of exploration and research, a clear genetic model has not yet been determined.
Gold Mineralization at the Detour Lake Deposit
At the Detour Lake mine, the gold mineralization is characterized into two main zones: hangingwall mineralization and footwall mineralization.
Hangingwall Mineralization
The mineralization forms a 200 metre wide (locally up to 350 metres) corridor within a broad assemblage of mafic volcanics with an overall east-west trend. To date, Detour Gold has drill tested this mineralized corridor for a distance of over five kilometres, west from the former Campbell pit. The bulk of the mineralization within this corridor is concentrated along a highly strained corridor of a moderate to strong potassic alteration envelope at the contacts between the pillowed mafic flows and massive flows.
At the eastern end of this corridor at the Detour Lake mine, the main mineralized zone is referred to as the Main Zone (terminology of the former Detour Lake mine). The Main Zone was the largest gold-bearing mineralized zone and consists of gold mineralization occurring in the CMH or in quartz and quartz-carbonate vein systems splaying from the SLDZ. Placer’s Quartz Zones Q50, Q70, Q100, and Q120 zones are typical quartz veins arrays splaying off the SLDZ into the hangingwall (Barclay, 1993). The former Campbell pit is located at the shallowest zone developed along the contact between massive Mg-rich tholeiitic volcanic and the pillowed Fe-rich tholeiitic volcanic. This system extends along strike to the west. In general, the quartz veins are part of a series of sub- vertically dipping east-west trending highly strained zones. These quartz veins are typically less than one metre in width. Gold occurs generally as free gold with these veins. The quartz veins commonly occur with a frequency of greater than one vein per metre. In plan view, these veins are commonly noted as a series of sheeted sub-parallel veins, which meet or intersect the SLDZ at 30° to 35° angles in the flexure area. These veins are commonly boudinaged and may locally post-date and cut folded foliation surfaces near the CMH (Pressacco, 1999). Textural features suggest the quartz veins and related auriferous zones have evolved late in the deformational history of the Detour Lake mine.
West of section 19,620E, the mineralization mainly straddles the lower massive flow-pillow flow contact and is commonly associated with increased biotite alteration, shearing, narrow quartz veining and minor pyrite or pyrrhotite. Local zones of strong brecciation with sulphide infilling have also been recognized along with minor chalcopyrite, telluride minerals and visible gold. Visible gold is usually found as specks, clusters or fracture coatings. The gold mineralization is associated with a series of sub-vertical to arcuate deformation zones characterized by enhanced strained fabrics, well defined open-space breccias, and to a lesser degree sheeted shear-hosted veins and extensional veins. Within these structures, pillow selvages and vesicles are preferentially sulphidized and contain visible gold. Mineralization is generally well distributed within this sequence but lithological changes to coarser and massive facies may locally affect continuity of the mineralization.
From sections 16,160E to 17,160E, Placer intersected the QK Zone along a massive flowpillow flow contact between 600 metres and 750 metres below surface. The QK Zone remains open down plunge and has not been tested below 800 metres. This mineralization is associated with narrow parallel to sub-parallel quartz veins, quartz boudins and sulphide rich veins/breccias with adjacent silicification and potassic alteration envelopes. Gold is directly associated with sulphides.
Footwall Mineralization (Talc Zone) (term used historically)
The Talc Zone is principally located between sections 19,700E and 20,540E (eastern end of the Detour Lake mine). It is hosted in highly altered (i.e. serpentinized and talcose) ultramafic flows with mineralization concentrated at both the upper contact (CMH), and lower contact of the SLDZ, next to barren volcaniclastics and mafic volcanics. The gold mineralization at the lower contact of the Talc Zone shows an increase in sulphide content. Locally, the mineralization is cut by felsic to intermediate intrusive dykes (ranging in width from 0.3 to 25 metres). The Talc Zone varies in width from 4 to 15 metres and tends to be less continuous along strike. The footwall mineralization commonly contains boudins of quartz veins and felsic as well as intermediate dyke slivers. It is generally intensely sheared, especially in the area adjacent to the contact with the volcanoclastic sediments.
Gold in the Talc Zone is dominantly associated with pyrite, pyrrhotite, and minor chalcopyrite along foliation planes, narrow discrete shears or strain zones, and in irregular lenses (Barclay, 1993). The zones also contain short deformed lenses or boudinaged quartz veins. In some cases, it appears that the mineralization is controlled by strong fault structures containing several centimetres of gouge material.
7.5.3 Gold Mineralization at the West Detour Deposit
The majority of the West Detour mineralization is closely associated with a moderately to
strongly sheared Mg-rich ultramafic komatiitic volcanic unit referred to by all previous
operators as the CG unit, a talc-chlorite schist. Shearing and gold mineralization in this
area extends several 10’s of metres north and south of this unit and generally it has been
referred to as the M Zone. The M Zone lies approximately 400 to 500 metres north of the
CMH and is a westerly trending gold system that is spatially associated with the margins of
the CG unit. The CG stratigraphic horizon and associated gold mineralization has been
traced by drilling for approximately 5 kilometres.
The footwall and hangingwall sequence of the CG are variably biotite altered with fairly abundant fractures and well-defined foliation (local veining) with associated pyrite, pyrrhotite, and rarely chalcopyrite. The mineralized zones appear lensoidal and plunge 20° west.
The gold mineralization styles are near identical as to the Detour Lake mine. Gold mineralization is within a relatively weak quartz vein stockwork with a low sulphide content (mainly pyrite and pyrrhotite).
Approximately 200 metres north of the M Zone, the North Walter Lake Zone (“NWLZ”) is in a zone of high strain with deformed quartz veins within pillowed to massive mafic volcanic flows. The NWLZ has been intersected by drilling between sections 16,100E and 17,200E (part of the North pit). The NWLZ gold mineralization is very similar to that found in the Detour Lake mine hanging wall sequence.
Source:
p.217
Summary:
Mining at Detour Lake is currently conducted using conventional open pit mining methods. The drill and blast, load and haul cycle uses an ‘Ultra Class’ mining fleet. Waste material is categorized then stored in various locations, typically segregated by material type (NAG, PAG, overburden, mineralized waste (low-grade) stockpiles). Ore is fed directly to the processing plant or stored in ROM stockpiles for processing at a future date.
Mining at the West Detour is planned to employ similar conventional mining methods with the initial use of smaller equipment for the pre-stripping phase, especially in overburden (starting in 2018). Once the majority of working faces have been advanced into hard rock, a mixture of Ultra-Class and smaller mining equipment will be used at West Detour.
Source:
p.240,241
Crusher / Mill Type | Model | Size | Power | Quantity |
Gyratory crusher
|
|
60" x 113"
|
1000 kW
|
1
|
Cone crusher
|
FLSmidth Raptor XL1100
|
|
745 kW
|
4
|
SAG mill
|
|
10.7m x 5.33m
|
7500 kW
|
2
|
Ball mill
|
|
7.73m x 12.19m
|
7500 kW
|
2
|
Summary:
Crushing and Grinding
The plant throughput was designed to average 55,000 tpd at 92% availability at a grind size of 95 µm.
The selected primary crushing system was a single stage, open circuit, primary gyratory crusher (60 x 113 inches). The crusher selection was based on a feed top size of 1,200 mm and a product P80 of 165 mm with an availability of 60% at 55,000 tpd. The live capacity of the feed and discharge hoppers of the gyratory crusher was designed for two truck loads each, assuming a nominal payload of 300 t.The crushed ore storage pile was designed with a live capacity corresponding to approximately 12 hours of crushing or 30,000 t, and an overall capacity (live plus dead) of 100,000 t.
Ore is reclaimed from the stockpile through two reclaim tunnels, one for each grinding line. Four apron feeders, two in each reclaim tunnel, discharge the crushed ore onto a belt conveyor that feeds a secondary cone crusher operated in open circuit. The secondary crusher is fed with the gyratory product with a P80 of 165 mm, and gives a product with a P80 of 50 mm. The secondary crusher product is conveyed directly to the SAG mill. The secondary crusher is equipped with a bypass chute to maintain high process plant availability. During maintenance of the secondary crusher, the bypass is put into place to feed the SAG mill directly from the stockpile.
The SAG mill operates in closed circuit with a pebble crusher while the ball mill operates in closed circuit with hydrocyclones. The total power required to grind ore to final ball mill product is fairly high at 23.3 kWh/t (25 kWh/t installed), reflecting the hardness of the ore
The design circulating load from the cyclones to the ball mill is 250% of the SAG mill new feed. This excludes the portion of the ball mill overflow, which is sent directly to the gold gravity recovery circuit. The pebble crushing circuit with a design discharge P80 of 13 mm processes the equivalent of up to 35% of the new SAG mill feed.
The SABC grinding system was designed for an average of 92% operating time. For benchmark comparisons, similar large SABC circuits around the world, with good maintenance practices and operator experience can achieve 94% operating time.
Processing
- Gravity separation
- Intensive Cyanidation Reactor (ICR)
- Smelting
- Centrifugal concentrator
- Carbon re-activation kiln
- Agitated tank (VAT) leaching
- Carbon in pulp (CIP)
- Solvent Extraction & Electrowinning
- Cyanide (reagent)
Flow Sheet:
Summary:
The processing plant was designed to process ore at an average throughput of 55,000 tpd or 20 Mt per year, equivalent to milling rates of 2,500 tpoh with operating time of 92% in a 24 hour day.
The processing plant started production in January 2013 with the first gold pour occurring in February 2013. Commercial production was declared on September 1, 2013. The design throughput of 55,000 tpd was surpassed in March 2015.
Gravity
Around 34% of the cyclone feed material is sent to the gravity recovery circuit based on GRG test work completed on the metallurgical samples. From the design criteria, the calculated tonnage going to the gravity circuits of the two lines is approximately 2,100 tpoh, from which the equipment was sized. Six gravity concentrators with 48 inch bowls were selected (three per grinding line supporting a strategy of two units in operation at all time). A batch intensive cyanidation system is used to process the gravity concentrate. The extraction performance of gold from the gravity concentrate by the intensive cyanidation system is designed at 99%. The pregnant solution is pumped to a tank in the gold room followed by electrowinning in a dedicated cell.
Leach and CIP
The gold recovery circuit selected was a “leach followed by a CIP” circuit. The designed retention time for leaching is 29 hours. The leach feed size was designed at a P80 of 95 µm.
The CIP design selected uses a carrousel type system with an average retention time of 80 minutes in this circuit. The carbon handling systems were designed to handle 20 t of carbon per strip. All the carbon transfers are done using recessed impeller pumps to minimize carbon abrasion.
Acid Wash, Stripping, Electrowinning, and Refining
The stripping system uses a modified version (i.e. on-line electrowinning and no pregnant solution tank) of the high-pressure Zadra process to recover the gold from the loaded carbon.
The circuit incorporates an acid wash stage and is designed to handle up to 10 t of carbon per day.
Based on the upgrading ratio expected in the CIP circuit at the provided operating conditions, one strip every two days per CIP line is required (2 CIP lines), which corresponds to one strip per day in total. The stripping circuit is designed to handle up to 20 t of carbon per stripping cycle (approximately 8-10 hours); 100% of the carbon is regenerated in two regeneration kilns designed to handle up to 20 t of carbon per day.
The electrowinning is done “in-line” with the stripping circuit. The flow of pregnant solution is split between three rows of two electrowinning cells. One dedicated electrowinning cell handles the pregnant solution from the high intensity leach circuit (ILR tank).
The refining equipment is designed to handle the gold from the stripping circuit and from the gravity recovery system. The electrowinning sludge is filtered, dried and mixed with fluxes, before being smelted using induction furnaces.
Recoveries & Grades:
Commodity | Parameter | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | 2014 |
Gold
|
Recovery Rate, %
| 91.3 | 92.1 | 90.1 | 90 | 89 | 91 | 91 |
Gold
|
Head Grade, g/t
| 0.8 | 0.92 | 1.04 | 0.93 | 0.9 | 0.88 | 0.88 |
Production:
Commodity | Units | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 |
Gold
|
koz
| 680-720 ^ | 517 | 602 | 621 | 571 | 538 | 506 |
All production numbers are expressed as metal in doré.
^ Guidance / Forecast.
Operational Metrics:
Metrics | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 |
Tonnes milled
| 21.1 Mt | 22 Mt | 20.7 Mt | 21.4 Mt | 20.8 Mt | 19.8 Mt |
Total tonnes mined
| | 106.3 Mt | 104.8 Mt | 100.1 Mt | 87.4 Mt | 90.7 Mt |
Ore tonnes mined
| | 21.3 Mt | 20.1 Mt | 19.7 Mt | 22.3 Mt | 23 Mt |
Waste
| | 85 Mt | 84.7 Mt | 80.4 Mt | 65.1 Mt | 67.7 Mt |
Daily milling rate
| | 60,370 t | 56,600 t | 58,508 t | 56,792 t | 54,114 t |
Stripping / waste ratio
| | 4 | 4.2 | 4.1 | 2.9 | 2.9 |
Daily mining rate
| | 291 kt | 287 kt | 274 kt | 239 kt | 249,000 t |
Reserves at December 31, 2020:
Mineral Reserves at Detour Lake were estimated at 13,821,000 ounces at an average grade of 0.96 g/t at an average cut-off grade above 0.5 g/t.
Mineral Resources for Detour Lake and West Detour project are based on a cut-off grade of 0.50 g/t Au.
Category | OreType | Tonnage | Commodity | Grade | Contained Metal |
Proven
|
In-Situ (OP)
|
83,747 kt
|
Gold
|
1.17 g/t
|
3,145 koz
|
Probable
|
In-Situ (OP)
|
512,369 kt
|
Gold
|
0.77 g/t
|
12,630 koz
|
Proven & Probable
|
In-Situ (OP)
|
596,115 kt
|
Gold
|
0.82 g/t
|
15,775 koz
|
Measured
|
In-Situ (OP)
|
21,285 kt
|
Gold
|
1.65 g/t
|
1,128 koz
|
Indicated
|
In-Situ (OP)
|
109,926 kt
|
Gold
|
1 g/t
|
3,529 koz
|
Indicated
|
In-Situ (UG)
|
2,900 kt
|
Gold
|
5.8 g/t
|
534 koz
|
Measured & Indicated
|
In-Situ (OP)
|
134,111 kt
|
Gold
|
1.2 g/t
|
5,191 koz
|
Measured & Indicated
|
In-Situ (UG)
|
2,900 kt
|
Gold
|
5.8 g/t
|
534 koz
|
Inferred
|
In-Situ (OP)
|
53,306 kt
|
Gold
|
0.93 g/t
|
1,606 koz
|
Inferred
|
In-Situ (UG)
|
1000 kt
|
Gold
|
4.35 g/t
|
136 koz
|
Commodity Production Costs:
| Commodity | Units | 2021 | 2020 | 2018 | 2017 | 2016 | 2015 |
Cash costs (sold)
|
Gold
|
USD
|
590 / oz ^
|
625 / oz
|
|
|
|
|
Total cash costs (sold)
|
Gold
|
USD
|
|
|
742 / oz
|
716 / oz
|
746 / oz
|
775 / oz
|
All-in sustaining costs (sold)
|
Gold
|
USD
|
|
1,171 / oz
|
1,158 / oz
|
1,064 / oz
|
1,007 / oz
|
1,056 / oz
|
^ Guidance / Forecast.
Financials:
| Units | 2020 | 2018 | 2017 | 2016 | 2015 | 2014 |
Sustaining costs
|
M USD
| 295.61 | 228.8 | 174.8 |
102.44
|
98.8
|
|
Capital expenditures
|
M USD
| 341.08 | | |
|
|
|
Revenue
|
M USD
| 960.85 | 776 | 707.8 |
658.29
|
563.02
|
535.79
|
Operating Income
|
M USD
| 369.55 | 145.7 | 161.5 |
94.9
|
12.7
|
-5.58
|
After-tax Income
|
M USD
| | 64.2 | 114.5 |
10.4
|
-42.07
|
-83.53
|
Heavy Mobile Equipment as of November 26, 2018:
Source:
p.235
HME Type | Model | Size | Quantity |
Dozer (crawler)
|
Caterpillar D10
|
|
5
|
Dozer (crawler)
|
Caterpillar D11
|
|
5
|
Dozer (crawler)
|
Caterpillar D9
|
|
2
|
Drill
|
Epiroc PV271
|
|
7
|
Drill
|
Epiroc D65
|
|
4
|
Drill
|
Epiroc DM45
|
|
2
|
Excavator
|
Caterpillar 349
|
|
2
|
Excavator
|
Caterpillar 385
|
|
4
|
Grader
|
Caterpillar 24M
|
|
1
|
Grader
|
Caterpillar 16M
|
|
3
|
Loader
|
Caterpillar 993
|
|
1
|
Loader
|
Caterpillar 992
|
|
1
|
Shovel (hydraulic)
|
Caterpillar 6060
|
28 cu. m
|
5
|
Shovel (hydraulic)
|
Caterpillar 6030
|
12 cu. m
|
2
|
Shovel (rope)
|
Caterpillar 7495
|
48 cu. m
|
2
|
Truck (haul)
|
Caterpillar 777
|
85 t
|
15
|
Truck (haul)
|
Caterpillar 795
|
300 t
|
36
|
Corporate Filings & Presentations:
News:
News | Date |
Kirkland Lake Gold Announces Filing of Detour Lake Technical Report, Including New Life-Of-Mine Plan
|
March 31, 2021
|
Kirkland Lake Gold Reports New Wide, High-Grade Intersections in Saddle Zone at Detour Lake, Confirms Continuity of Mineralization Between Main and West Pits
|
March 15, 2021
|
Kirkland Lake Gold Reports Strong Fourth Quarter and Full-Year 2020 Production, Company Repurchases 20 Million Shares
|
January 12, 2021
|
Kirkland Lake Gold Reports Additional High-Grade Intersections at Detour Lake Saddle Zone
|
September 9, 2020
|
Kirkland Lake Gold Intersects High Grades and Extends Mineralization at Detour Lake Main Pit and 58 North Zone
|
June 29, 2020
|
Kirkland Lake Gold Completes Acquisition of Detour Gold
|
January 31, 2020
|
Kirkland Lake Gold Completes Acquisition of Detour Gold
|
January 31, 2020
|
Kirkland Lake Gold to Add New Cornerstone Asset Through Acquisition of Detour Gold, Grows Free Cash Flow, Mineral Reserves and Production
|
November 25, 2019
|
Detour Gold Files Technical Report for Detour Lake
|
November 26, 2018
|
Detour Gold Provides Updated Life of Mine Plan and Reaffirms Commitment to Optimizing Detour Lake Operation
|
June 28, 2018
|