The Xuxa Deposit will be mined by open pit mining methods, using a contracted mining fleet consisting of hydraulic excavators, front loaders, and 40 t transport trucks for waste and ore, coupled with appropriate auxiliary support equipment.
The mine layout and operation are based on the following criteria:
• Two independent open pits areas: Pit 1 in the north and Pit 2 in the south;
• Single access from both pits to the mine infrastructure pad and the processing plant;
• Pre-splitting of the ore zone to reduce mine dilution;
• Elevated inter-ramp angles for the waste to reduce strip ratio.
The basis for the scheduling includes:
• Six months of pre-stripping to liberate the ore;
• Pit 1 and Pit 2 mined in conjunction from Year 1 to Year 8 to reduce the drop-down rate and to facilitate the 1.5 Mtpa production rate;
• The planned open pit mine life is eight years;
• The mining fleet is based on road trucks and this fleet will be operated by a mining contractor.
The main mining activities will be:
- Digging or rock blasting of ore and waste;
- Excavation, loading and transport of ore and waste;
- Disposal of ore in the ROM yard and waste in the waste dump;
- Construction and maintenance of all internal accesses to the pit(s) and the waste dumps;
- Maintenance of the floor, drainage, coating and signaling of all access roads used in the operation;
- Implementation and maintenance ........