Overview
Stage | Production |
Mine Type | Open Pit |
Commodities |
|
Mining Method |
|
Processing |
- Gravity separation
- Centrifugal concentrator
- Smelting
- Carbon re-activation kiln
- Crush & Screen plant
- Inline Leach Reactor (ILR)
- Agitated tank (VAT) leaching
- Carbon in leach (CIL)
- Carbon adsorption-desorption-recovery (ADR)
- Elution
- Solvent Extraction & Electrowinning
- Filter press
- Cyanide (reagent)
|
On-Site Camp |
yes |
Production Start | 2005 |
Mine Life | 2025 |
Damang mine is approaching the end of the successfully implemented Damang Reinvestment Project (DRP). Mining operations are planned to end in 2023 after the depletion of the Huni pit, while processing of stockpiles is planned to continue until 2025.
LOM extension scoping studies aimed at identifying possible value-adding opportunities for the mine were approved to advance to a prefeasibility level of study during 2022. The PFS is assessing the viability of a further pushback at the east wall of the main Damang pit and Juno Pit immediately to the south to exploit the remainder of the ore body. Work is also under way in the area south of the Juno pit to assess the potential of the Nyame and Tamang deposits to improve the value of the LOM plan. |
Source:
p. 100,201
Company | Interest | Ownership |
Government of Ghana
|
10 %
|
Indirect
|
Gold Fields Ltd.
|
90 %
|
Indirect
|
Gold Fields Limited owns 90% of the issued shares of Abosso Goldfields Ltd. (AGL), with the Ghanaian government owning the remaining 10% free carried interest.
Contractors
Contractor | Contract | Description | Ref. Date | Expiry | Source |
Engineers and Planners Company Ltd (E&P)
|
Mining
|
Mining operations are carried out by contract mining.
E&P is currently engaged as the contractor working the mines for Goldfields at Damang.
|
Jul 28, 2020
|
|
|
Genser Energy
|
Power supply
|
The Damang mine completed its transition from the national grid to an independent power producer, Genser Energy, during 2017. Genser Energy commissioned the last of the units at its Damang gas plant in February 2017 and now supplies 27.5MW of energy, which accounts for Damang’s total electricity consumption. The mine still has access to the ECG, a national grid energy provider, as a back-up.
|
Dec 31, 2022
|
|
|
Deposit Type
- Hydrothermal
- Vein / narrow vein
- Paleoplacer
Source:
p.32-34
Summary:
Two epigenetic gold forming events are identified in Ghana. A pre-Tarkwaian event which provided the protolith of the world class Tarkwaian palaeoplacer deposits, and a post-Tarkwaian deformation event which, led to the formation of orogenic hydrothermal gold deposits in Ghana and other West African countries.
Damang exploits oxide and primary zone orogenic style hydrothermal mineralisation in addition to palaeoplacer mineralisation. The post-Tarkwaian phase of hydrothermal mineralisation overprints the lower grade Tarkwaian palaeoplacer conglomerates.
Palaeoplacer mineralisation
Three main gold-bearing conglomerate horizons are recognized on the limbs of the Damang Anticline within the Banket Series of the Tarkwaian Group. From footwall to hanging-wall (i.e., oldest to youngest), these are the Star/Composite, Malta/Breccia, and Gulder Reefs on the west limb and the Lima, Kwesie-K1 and Kwesie-K2 Reefs on the east limb. The conglomerate horizons on both limbs are separated by poorly mineralized sandstone units. The reefs are usually characterized by an upward fining sequence of poor to moderately sorted, clast supported polymictic conglomerates. However, local variations are observed where the conglomerate domain is interbedded with fine to coarse-grained sandstones. The conglomerates host gold grades that range from 1.3 g/t Au to 1.5 g/t Au whereas the sandstone units usually contain grades of between 0.1 g/t Au to 0.2 g/t Au.
Hydrothermal mineralisation
A significant portion of the gold mineralisation at the Damang pit is associated with hydrothermal mineralisation, with veins being the principal sources of ore. The mineralisation at Damang formed in response to progressive Dz (NNWW-SSE) shortening and compression, with mineralisation occurring after peak regional metamorphism at around 2058 Ma (Tunks et al., 2004). Gold mineralisation is associated with hydrothermal alteration halos around auriferous quartz veins.
Two main controls on the distribution of the alteration signature have been identified. Structural fracturing controls the distribution of veins and therefore the distribution of localized alteration, and primary lithology, which concentrates alteration along bedding foresets in the Banket Footwall, particularly in the heavy mineral foresets of the Banket Series sandstones.
Compressional deformation controlled the development of the structures that provided fluid pathways for the localization of hydrothermal fluids. Veins occur in two general styles which are gradational with one another, extension veins and shear veins - with their associated alteration envelopes.
Extensional veins comprise en-échelon arrays of sigmoidal vein arrays that form stacked sub-horizontal vein sets between shear veins (fault-fracture mesh) or at shear vein tips (Rhys, 2019). They vary from 0.5 to 20 cm thick white to glassy clear quartz veins that have simple blocky quartz fill and sharp contacts with the wall rock. These veins are lenticular in cross section and lack foliation or banding. They vary to carbonate rich in areas outside of ore zones, where they lack alteration and gold-mineralisation.
Shear veins are generally sub-parallel to bedding and vary in thickness from <2 cm to 0.7 m and have a more banded or complex fill of white quartz with wall rock slivers and layers, trails, bands and stylolites of sulphides, tourmaline and sericite-Fe-carbonate. Gold occurs as free grains, typically associated with sulphides and as a refractory component in pyrite. Discontinuity of mineralisation is inherent, due to the én-echelon arrangement of the veins within the shear zone as well as the highly sheared and disrupted nature of such zones.
The veins are cross-cut lithologies and are mainly confined to the silicified Banket Series units as well as in the Tarkwa Phyllites, Intrusives and to a lesser extent the Huni Sandstone units.
Since reddish albite was observed to occur in vein selvages and envelopes in many areas, at least some of this alteration is associated with syn-ore hydrothermal fluid flow. Broader areas could represent more distributed, earlier hydrothermal activity that is a precursor to the areas of vein development, but still indicative of hydrothermal corridors, as is commonly present in other orogenic gold systems.
Damang is a world class gold mineralisation system where drilling has only tested to relatively shallow depths along known ore-bearing corridors in the Tarkwaian sediments on the margins of the Damang Anticline. Within this corridor and in the adjacent Birimian rocks there may be additional potential for new orebodies in both a near-mine setting and at a brown fields district scale in the following general areas:
- Stacked mineralisation potential
Potential exists for additional stacked areas of mineralisation to be identified, which could form deep pit or underground exploration targets below the currently mined and drilled levels. Given the presence of continuous higher grade zones apparent in the resource definition drilling assays, there is potential for underground selective mining of concentrated vein arrays and shear veins if additional zones either below, down plunge of or between the pit areas can be identified. Stacked zones of mineralisation may locally have vertical gaps, so even if gold grades and vein intensity diminish immediately under currently mined areas, these could pick up at depth, especially if additional folds or shear zones are present. Further to this, if additional reverse faults like the West Birimian Fault underlie, and control the positions of folds west of Amoanda, these could be prospective targets for shallow plunging zones where veins have developed adjacent to or above the faults.
- Birimian mineralisation potential
Current mining and exploration at Damang has primarily concentrated on the Tarkwaian sequence. Given the potential for Birimian hosted ore implied by other deposits in the region, there may be potential for mineralisation in this sequence, especially where competent units such as intrusions or mafic flows occur in weaker rocks, forming a rheological contrast that could focus shear zones and vein arrays. This potential is exemplified by the presence of mineralisation in a small intrusive body which was mined in the Birimian rocks in the eastern portion of the Amoanda pit.
Source:
p.103-104
Summary:
Mining operations are carried out by contractor miners using open-pit, conventional drill and blast with truck and shovel methods. Since December 2022, mining is focused on the Huni pit. Gold mineralisation is mined to a selective COG and segregated into grade ranges to balance ore production and processing capacities. The pit walls are monitored by radar to mitigate geotechnical challenges, with additional controls implemented to ensure safe operations.
Damang has one open pit constituting the Mineral Reserves, seven open pits comprising the Mineral Resources, one ore stockpile.
In open pit mining, access to the orebody is achieved by stripping the overburden in benches of fixed height to expose the ore below. This is most typically achieved by drilling and blasting an area, loading the broken rock with excavators into dump trucks and hauling the rock and/or soil to dumps. The overburden material is placed on designated waste rock dumps.
Extraction of the orebody involves a similar activity as in stripping the overburden. Lines are established on the pit floor demarcating ore from waste material and the rock is then drilled and blasted. Post blasting, the ore is loaded into dump trucks, based on a defined ‘dig plan’ demarcating the position of the ore and waste boundaries post the heave and throw movement caused by the blasting, and hauled to interim stockpiles or directly to the crusher at the process plant, while the waste is hauled to waste rock dumps.
Mining at Damang is carried out using conventional open pit methods. This has been the preferred mining method since the commencement of the mine in 1997 due to the characteristics of the ore deposit. The outcome of a scoping study undertaken in 2020 on the future of Damang supported the economic and technical viability of the open pit mining methods under prevailing conditions due to the modelled underground low tonnages of the sparsely distributed ore domains above estimated underground cut-off grades in the major reefs of the Damang pit.
Damang’s life of mine plan is based on a contractor mining model. Mining is planned to end in 2023 with processing of stockpiles until 2025. Grade control drilling precedes production drilling and blasting. Fresh rock and transitional zones are drilled and blasted as 9 m benches that are excavated in 3 m flitches. Oxide material which cannot be “freedug” is blasted using lower powder factors. Conventionally, Nonel detonators and emulsion are used in both fresh and oxide material. However, electronic detonators are used to control the impact of blasting on the pit walls in areas where there are geotechnical challenges. Presplit wall control methods and trim blasting are also used in the fresh zones to ensure stability of the pit walls. CAT 777 trucks haul the ore to the run-of-mine pad and waste to the respective planned dumps.
Dewatering in the Damang and Huni pits, as well as the surface drains and sumps, is undertaken by a combination of diesel and electric pumps. The current annual discharge capacity is about 4 Mm3. The water is discharged into the Lima, Kwesie and Tomento pits and later pumped to the Adjaye dam to serve as raw water source for the processing plant or for dust suppression. Alternatively, when the water quality meets regulatory standards, the water is discharged into the environment.
Equipment and labour requirements
Primary loading is completed by Liebherr R9250 (250 t) and Hitachi 1900-6 (190 t) excavators. Primary haulage is completed with Cat 777F/G (90 t). Major equipment is modelled with an availability of 84 % to 86 % and use of availability of 85 %.
Mining is a continuous operation with 3 crews on 2 X 12-hour shifts.
Mine design
The west wall of the Damang pit includes 80 ° batters at a height of 18 m separated by 6 m wide berms. This geometry produces a 63 ° crest-to-crest inter ramp slope angle. The highest uninterrupted inter-ramp slope (126 m high) is located at 26,000 N. The current life of mine design includes ramp switchbacks and other slope decoupling step-outs that create a nominal overall slope angle of 52 ° (a slope section located at 26,000 N has a design crest-to-toe angle of 53 ° at a height of 337 m) in the hard rock zone.
The configuration of the east wall of the Damang pit includes 65 ° batters at a height of 18 m separated by 6 m wide berms. This geometry produces a 52 ° crest-to-crest inter ramp slope angle and nominal overall slope of 46 ° at a slope section located at 25,900 N at a height of 360 m.
The Huni pit includes 75 ° and 65 ° batters at the west and east walls respectively. The highest uninterrupted interramp slope produces 57° crest-to-crest inter ramp slope angle at 26,630 N at a height of 108 m and overall slope angle of 51 ° at 26,920 N at a height of 141 m on the west wall. The configuration of the east wall produces an overall slope angle of 44 ° at 26,980 N at a height of 142 m.
Mining in the Damang main pit was completed in 2022 and the Huni pit mining is scheduled to be completed in 2023.
Source:
Source:
- subscription is required.
Processing
- Gravity separation
- Centrifugal concentrator
- Smelting
- Carbon re-activation kiln
- Crush & Screen plant
- Inline Leach Reactor (ILR)
- Agitated tank (VAT) leaching
- Carbon in leach (CIL)
- Carbon adsorption-desorption-recovery (ADR)
- Elution
- Solvent Extraction & Electrowinning
- Filter press
- Cyanide (reagent)
Flow Sheet:
Source:
p.91-93
Summary:
The processing plant treats predominantly fresh ore, comprising a three-stage crushing circuit, SAG/ball mill with a pebble crushing circuit, a gravity recovery circuit and a CIL gold recovery circuit. The plant has been optimised to process 4.6Mtpa.
The gravity circuit comprises two XD48" Knelson concentrators with dedicated InLine Leach Reactor for intensive cyanidation of the gravity concentrate. The gravity circuit recovers approximately 30 % of the gold. The leached tails from the ILR reports to the Ball Mill for regrinding after the clarified pregnant solution has been transferred to the electrowinning circuit and the remaining solids have been subjected to several wash cycles using raw water.
The leach circuit comprises eight tanks in series, each with a nominal capacity of 3,000 m3 providing a retention time of 3.7 hours per tank. Each tank is fitted with two cylindrical inter tank screens (Kemix MPS 750P type 1 mm apertures) with mechanical wiper blades to keep carbon away from the screen surface and dual open impellers. The loaded carbon is recovered from CIL tank 1 into the acid wash column and acid washed using 3 % strength hydrochloric acid followed by water flushing.
The rinsed carbon is transferred to the elution column where a hot caustic solution (3 % concentration) is circulated through the column via heat exchangers to elute the gold absorbed on the carbon. Elution is carried out at 120 °C at an operating pressure of 350 kPa in the column. The dissolved gold is then electro-deposited onto stainless steel wool cathodes. Barren carbon from the elution circuit is regenerated in a carbon regeneration kiln.
Gold sludge from both the gravity and electrowinning circuits is washed and filtered. The sludge is further refined through smelting and crude doré is poured. Gravity doré bars are approximately 90 % to 95 % gold whereas doré bars from the CIL circuit are dependent on ore feed characteristics and can vary between 65 % and 90 % gold. Doré is dispatched to a refinery for further processing into gold bullion.
Recoveries & Grades:
Commodity | Parameter | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 |
Gold
|
Recovery Rate, %
| 92 | 93 | 91 | 92 | 94.1 | 92.2 | 91.9 |
Gold
|
Head Grade, g/t
| 1.6 | 1.8 | 1.6 | 1.51 | 1.42 | 1.05 | 1.18 |
Source:
- subscription is required.
Production:
All production numbers are expressed as metal in doré.
^ Guidance / Forecast.
Operational Metrics:
Metrics | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 |
Annual processing capacity
| 4.6 Mt | 4.6 Mt | 4.5 Mt | 4.5 Mt | | 4.2 Mt |
Stripping / waste ratio
| 2.6 | 1.9 | 3.4 | 6.29 | 9.22 | 10.9 |
Ore tonnes mined
| 5,872 kt | 8,271 kt | 6,680 kt | 4,680 kt | 4,495 kt | 3,329 kt |
Waste
| 15,435 kt | 15,752 kt | 22,549 kt | 29,418 kt | 41,442 kt | 36,397 kt |
Total tonnes mined
| 21,308 kt | 24,023 kt | 29,229 kt | 34,098 kt | 45,937 kt | 39,726 kt |
Tonnes milled
| 4,784 kt | 4,720 kt | 4,798 kt | 4,645 kt | 4,205 kt | 4,590 kt |
Daily processing capacity
| | | 12,600 t | | | |
Reserves at December 31, 2022:
Mineral Reserves cut-off for fresh ore 0.67 – 0.75 g/t and for oxide ore 0.56 – 0.64 g/t;
Mineral Resources cut-off for fresh ore 0.61 – 0.86 g/t and for oxide ore 0.52 – 0.66 g/t.
Category | OreType | Tonnage | Commodity | Grade | Contained Metal |
Proven
|
Stockpiles
|
8,241 kt
|
Gold
|
0.8 g/t
|
219 koz
|
Proven
|
In-Situ (OP)
|
329 kt
|
Gold
|
1.2 g/t
|
12 koz
|
Proven
|
Total
|
8,569 kt
|
Gold
|
0.8 g/t
|
232 koz
|
Probable
|
In-Situ (OP)
|
1,758 kt
|
Gold
|
1.3 g/t
|
75 koz
|
Proven & Probable
|
In-Situ (OP)
|
2,087 kt
|
Gold
|
1.3 g/t
|
87 koz
|
Proven & Probable
|
Total
|
10,328 kt
|
Gold
|
0.9 g/t
|
307 koz
|
Measured
|
Stockpiles
|
2 kt
|
Gold
|
0.6 g/t
|
0.4 koz
|
Measured
|
In-Situ (OP)
|
3,697 kt
|
Gold
|
1.7 g/t
|
207 koz
|
Measured
|
Total
|
3,699 kt
|
Gold
|
1.7 g/t
|
207 koz
|
Indicated
|
In-Situ (OP)
|
39,684 kt
|
Gold
|
2.1 g/t
|
2,688 koz
|
Measured & Indicated
|
Total
|
43,383 kt
|
Gold
|
2.1 g/t
|
2,895 koz
|
Inferred
|
Stockpiles
|
1,151 kt
|
Gold
|
0.6 g/t
|
22 koz
|
Inferred
|
In-Situ (OP)
|
8,050 kt
|
Gold
|
2 g/t
|
527 koz
|
Inferred
|
Total
|
9,201 kt
|
Gold
|
1.9 g/t
|
549 koz
|
Commodity Production Costs:
| Commodity | Units | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 |
All-in sustaining costs (sold)
|
Gold
|
USD
|
1,830 / oz ^†
|
998 / oz†
|
802 / oz†
|
1,008 / oz†
|
809 / oz†
|
813 / oz†
|
All-in costs
|
Gold
|
USD
|
1,830 / oz ^†
|
1,083 / oz†
|
852 / oz†
|
1,035 / oz†
|
1,147 / oz†
|
1,506 / oz†
|
^ Guidance / Forecast.
† Net of By-Product.
Financials:
| Units | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 |
Capital expenditures (planned)
|
M USD
| 7 | | | |
|
|
|
Growth Capital
|
M USD
| | 10 | 6 | 6 |
|
|
|
Sustaining costs
|
M USD
| | 49.6 | 17.4 | 14 |
5.8
|
14
|
17.2
|
Capital expenditures
|
M USD
| | 60.1 | 23.4 | 20 |
76.3
|
139
|
132
|
Revenue
|
M USD
| | 414.8 | 457.5 | 400.8 |
288.3
|
229
|
180.3
|
After-tax Income
|
M USD
| | 85.7 | 98.7 | 45.2 |
25.5
|
-8.3
|
20.4
|
Heavy Mobile Equipment as of December 31, 2021:
Source:
p.90
HME Type | Model | Size |
Drill
|
Sandvik DP1500i
|
|
Drill
|
Sandvik Leopard™ DI550
|
|
Excavator
|
Liebherr R 9250
|
250 t
|
Excavator
|
Hitachi EX1900
|
190 t
|
Truck (dump)
|
Caterpillar 777
|
90 t
|
Mine Management:
Job Title | Name | Profile | Ref. Date |
Metallurgical Manager
|
Catherine Kuupol Kuutor
|
|
Aug 23, 2023
|
Mine Planning Manager
|
John Ankomah
|
|
Aug 23, 2023
|
Mining Manager
|
Charles Kofi Nti
|
|
Aug 23, 2023
|
Project Superintendent
|
Caleb Dzasa
|
|
Aug 23, 2023
|
Supply Chain Manager
|
Emmanuel Kingsley Arthur
|
|
Aug 23, 2023
|
Staff:
Employees | Contractors | Total Workforce | Year |
405
|
1,749
|
2,154
|
2022
|
Corporate Filings & Presentations: